6535 W MELROSE AVE #102 90038
Certificate Information: 6535 W MELROSE AVE #102 90038
- Application / Permit
- 22016-10000-11312
- Plan Check / Job No.
- B22LA06597
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- INTERIOR T.I TO (E) (2785 s.f. ) RESTAURANT WITH 385 s.f OF OUTDOOR DINING AREA
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/13/2024
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | GARO TELMI |
| Corrections Issued | 5/11/2022 | GARO TELMI |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Applicant returned to address corrections | 6/14/2022 | GARO TELMI |
| Plan Check Approved | 8/10/2022 | GARO TELMI |
| Issued | 8/26/2022 | APPLICANT |
| Permit Finaled | 3/11/2024 | TIMOTHY POWELL |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/14/2022 | STEVE MELGAR |
| Fire Marshal Fire Life Safety | Cleared | 5/21/2022 | MENOA AGHAJANI |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | STEVE MELGAR |
| Food establishment approval | Cleared | 6/9/2022 | LACDHS APPROVED |
| DAS Clearance | Cleared | 6/16/2022 | GARO TELMI |
| Green Code | Cleared | 6/22/2022 | AARON COSTA |
| Food Service Establishment | Cleared | 6/23/2022 | RAMESHBHAIR PATEL |
| Miscellaneous | Cleared | 7/14/2022 | MARYAM SAEDI |
| Sewer availability | Cleared | 7/22/2022 | STEVE MELGAR |
Contact Information
| Architect | Leach,, Blair S; Lic. No.: C25788 | 3631 NORTH KATMAI MESA, AZ 852150895 |
| Contractor | Umholtz J R Framing; Lic. No.: 722480-B | 177 E 22ND STREET 9 COSTA MESA, CA 92627 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/7/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| Insulation | 12/14/2022 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 12/20/2022 | Partial Inspection | VAHE KELEDJIAN |
| Light Gage Steel Frame | 12/20/2022 | Corrections Issued | VAHE KELEDJIAN |
| Light Gage Steel Frame | 12/21/2022 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 2/1/2023 | Corrections Issued | JEROME BLACKWOOD |
| T-Bar Ceiling | 2/10/2023 | Not Ready for Inspection | JAIME RIOS |
| T-Bar Ceiling | 2/16/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 9/22/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 11/30/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 3/4/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 3/4/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Final | 3/4/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 3/4/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 3/11/2024 | Partial Inspection | TIMOTHY POWELL |
| Final | 3/11/2024 | Permit Finaled | TIMOTHY POWELL |
| Green Building Final | 3/11/2024 | Approved | TIMOTHY POWELL |
| METHANE-Final | 3/11/2024 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 3/11/2024 | Approved | TIMOTHY POWELL |