11010 N MARKLEIN AVE 91345

Certificate Information: 11010 N MARKLEIN AVE 91345

Application / Permit
22016-10000-11265
Plan Check / Job No.
B22LA06567
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED [18 x 20] GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/26/2022 JESSE JIMENEZ
Corrections Issued 4/27/2022 JESSE JIMENEZ
Building Plans Picked Up 5/3/2022 APPLICANT
Applicant returned to address corrections 10/14/2022 LUKE GONZALES
Plan Check Approved 10/18/2022 ADAM HEGAZI
Issued 10/18/2022 APPLICANT
CofO in Progress 3/2/2023 JENNIFER RABUCHIN
No Progress 3/28/2023 ROBERT GOLD
CofO in Progress 3/29/2023 ROBERT GOLD
Permit Finaled 4/6/2023 MICHAEL SMITH
CofO Issued 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/9/2022 CARLOS AGUILERA
Permit Cleared 5/9/2022 CARLOS AGUILERA
Sewer availability Cleared 5/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/13/2022 CARLOS AGUILERA
Construction near power lines Cleared 10/14/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2022 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 10/28/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/4/2022 Partial Inspection JENNIFER RABUCHIN
Green Building Rough 11/4/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 11/4/2022 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/1/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 12/1/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 12/1/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 12/1/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 12/1/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/8/2022 Approved JENNIFER RABUCHIN
Green Building Rough 12/8/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 12/8/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/8/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/14/2022 Corrections Issued JENNIFER RABUCHIN
Insulation 12/14/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/29/2022 Approved JENNIFER RABUCHIN
Insulation 12/29/2022 Approved JENNIFER RABUCHIN
Service/Power Release 12/29/2022 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 1/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 1/9/2023 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 1/20/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 2/13/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 2/13/2023 Approved JENNIFER RABUCHIN
Green Building Final 2/13/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/13/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/1/2023 Approved JENNIFER RABUCHIN
Final 3/1/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/1/2023 Approved JENNIFER RABUCHIN
HVAC-Final 3/1/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 3/1/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/1/2023 Approved JENNIFER RABUCHIN