3322 W LARGA AVE 90039

Certificate Information: 3322 W LARGA AVE 90039

Application / Permit
22016-10000-11140
Plan Check / Job No.
B22LA06503
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR STRUCTURAL REMODEL OF EXISTING 1-STORY SFD. REPLACE PORTION OF ROOF FRAMING.
Permit Issued
Issued on 6/1/2022
Issuing Office
Metro
Current Status
Permit Finaled on 3/24/2023

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 MAHNAZ NOURHASHEMI
Corrections Issued 5/18/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 5/18/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 6/1/2022 MAHNAZ NOURHASHEMI
Issued 6/1/2022 APPLICANT
Permit Finaled 3/23/2023 COREY HUPP

Permit Application Clearance Information

ZI Cleared 5/19/2022 LOUIS ORTEGA
Roof/Waste drainage to street Cleared 5/23/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/24/2022 AMAAN MALIK

Contact Information

Contractor Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B 13506 ALANWOOD ROAD      LA PUENTE, CA 91746
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/16/2022 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 6/22/2022 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/23/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/23/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/28/2022 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval COREY HUPP
Deputy Wood Construction 8/18/2022 No Access for Inspection COREY HUPP
ELECTRICAL-Rough 8/26/2022 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 8/26/2022 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 8/30/2022 Partial Approval COREY HUPP
PLUMBING-Rough 8/30/2022 Partial Approval COREY HUPP
Deputy Wood Construction 8/31/2022 Conditional Approval COREY HUPP
BUILDING-Rough-Frame 9/6/2022 Not Ready for Inspection ROBERT CHAVEZ
ELECTRICAL-Rough 9/6/2022 Corrections Issued ROBERT CHAVEZ
HVAC-Rough 9/6/2022 Corrections Issued ROBERT CHAVEZ
PLUMBING-Rough 9/6/2022 Corrections Issued ROBERT CHAVEZ
BUILDING-Rough-Frame 9/13/2022 Approved COREY HUPP
Rough-Elec/Plmb/HVAC 9/13/2022 Partial Approval COREY HUPP
Interior/Exterior Lathing 9/19/2022 Approved ROBERT CHAVEZ
HVAC-Rough 9/22/2022 Approved COREY HUPP
Insulation 9/22/2022 Approved COREY HUPP
Drywall Nailing 9/29/2022 Approved COREY HUPP
Interior/Exterior Lathing 10/12/2022 Approved COREY HUPP
Shower Pan 10/12/2022 Approved COREY HUPP
Final 2/28/2023 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved COREY HUPP
Smoke Detectors 2/28/2023 Approved COREY HUPP
Final 3/8/2023 Not Ready for Inspection COREY HUPP
Final 3/20/2023 Corrections Issued COREY HUPP
Final 3/23/2023 Permit Finaled COREY HUPP