8555 N INDEPENDENCE AVE 1-35 91304

Certificate Information: 8555 N INDEPENDENCE AVE 1-35 91304

Application / Permit
22016-10000-11103
Plan Check / Job No.
B22LA06476
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERSION OF (E) ATTACHED CAR GARAGES INTO SIX (6) ADUS ON (E) 29 UNIT APT BUILDING PER CA GOVT CODE 65852.2 (E)(1)(C). SEE COMMENT.
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 TSE MING HUANG
Corrections Issued 5/19/2022 TSE MING HUANG
Quality Review Completed 5/26/2022 KEN GILL
Building Plans Picked Up 6/9/2022 APPLICANT
Disabled Access Plans Picked Up 6/14/2022 APPLICANT
Applicant returned to address corrections 12/6/2022 TSE MING HUANG
Applicant returned to address corrections 12/15/2022 TSE MING HUANG
Plan Check Approved 1/5/2023 TSE MING HUANG
Issued 1/17/2023 APPLICANT
CofO in Progress 2/14/2024 DEANDRE HOFFMAN
CofO Issued 2/27/2024 JEFFREY DURAN
Permit Finaled 2/27/2024 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 6/13/2022 CARLOS AGUILERA
Sewer availability Cleared 6/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/16/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/7/2022 LAVEON RIDER
Fire Marshal Fire Life Safety Cleared 11/9/2022 VIDAL GARCIA
DAS Clearance Cleared 11/16/2022 TSE MING HUANG

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Rent Ready Construction Inc; Lic. No.: 1065376-B 631 N SIERRA BONITA AVE      LOS ANGELES, CA 90036

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/7/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/7/2023 Approved CAMERON CHABAN
Special/Order Compliance 2/7/2023 Approved STEVEN LEVITT
Wood Frame 3/31/2023 Partial Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 4/5/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 6/29/2023 Corrections Issued DEANDRE HOFFMAN
Wood Frame 7/7/2023 Partial Inspection DEANDRE HOFFMAN
Insulation 7/19/2023 Partial Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 7/19/2023 Not Ready for Inspection DEANDRE HOFFMAN
Drywall Nailing 7/25/2023 Partial Approval STEVEN LEVITT
Interior/Exterior Lathing 7/25/2023 Approved STEVEN LEVITT
Drywall Nailing 8/4/2023 Approved JEFFREY FULTON
Final 10/20/2023 Corrections Issued DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 10/20/2023 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 10/20/2023 Approved DEANDRE HOFFMAN
Final 2/12/2024 OK to Issue CofO DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 2/12/2024 Approved DEANDRE HOFFMAN