2844 N COOLIDGE AVE 90039

Certificate Information: 2844 N COOLIDGE AVE 90039

Application / Permit
22016-10000-11091
Plan Check / Job No.
B22LA06465
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing permitted Garage/Rec. Room to 423 SF Accessory Dwelling Unit. * NO NEW AREA PROPOSED*
Permit Issued
Issued on 2/27/2023
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 DANIEL YIP
Corrections Issued 4/15/2022 CARLOS MONTES
Plan Check Approved 8/7/2022 DANIEL YIP
Issued 2/27/2023 APPLICANT
CofO in Progress 6/30/2023 THOMAS LOGRASSO
Permit Finaled 7/8/2023 DEROLD HAUFF
CofO Issued 7/8/2023 DEROLD HAUFF
Permit Finaled 7/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/12/2022 JENSON LEE
Sewer availability Cleared 5/12/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JENSON LEE
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY

Contact Information

Architect Rodriguez,, Hector Manuel; Lic. No.: NA39395       ,
Contractor Maven Associates Inc The; Lic. No.: 1085625-B       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/30/2023 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 4/5/2023 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/5/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 4/5/2023 Approved THOMAS LOGRASSO
Sewer 4/5/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 4/21/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/21/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 4/21/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 4/21/2023 Corrections Issued KATHRYN BUTTERWORTH
Insulation 4/21/2023 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 4/21/2023 Approved KATHRYN BUTTERWORTH
Shower Pan 4/21/2023 Approved KATHRYN BUTTERWORTH
Wood Frame 4/21/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 5/1/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/4/2023 Partial Approval THOMAS LOGRASSO
Final 6/14/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 6/14/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 6/14/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 6/23/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/23/2023 Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/23/2023 Approved ALIZAH MAYAGOITIA
Final 6/29/2023 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 6/29/2023 Approved THOMAS LOGRASSO