2844 N COOLIDGE AVE 90039
Certificate Information: 2844 N COOLIDGE AVE 90039
- Application / Permit
- 22016-10000-11091
- Plan Check / Job No.
- B22LA06465
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing permitted Garage/Rec. Room to 423 SF Accessory Dwelling Unit. * NO NEW AREA PROPOSED*
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2022 | DANIEL YIP |
| Corrections Issued | 4/15/2022 | CARLOS MONTES |
| Plan Check Approved | 8/7/2022 | DANIEL YIP |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 6/30/2023 | THOMAS LOGRASSO |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
| CofO Issued | 7/8/2023 | DEROLD HAUFF |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/12/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2022 | JENSON LEE |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Architect | Rodriguez,, Hector Manuel; Lic. No.: NA39395 | , |
| Contractor | Maven Associates Inc The; Lic. No.: 1085625-B | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/30/2023 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 4/5/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/5/2023 | Approved | THOMAS LOGRASSO |
| Sewer | 4/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/21/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Insulation | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 4/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 5/1/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Final | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/23/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/23/2023 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/23/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/29/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 6/29/2023 | Approved | THOMAS LOGRASSO |