2432 E 8TH ST 90021
Certificate Information: 2432 E 8TH ST 90021
- Application / Permit
- 22016-10000-10962
- Plan Check / Job No.
- B22LA06340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE FROM (E) WAREHOUSE TO OFFICE & NEW MEZZANINE ADDITION & MAJOR REMODEL .
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2022 | APPLICANT |
| Green Plans Picked Up | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | GARO TELMI |
| Corrections Issued | 5/4/2022 | GARO TELMI |
| Quality Review Completed | 5/12/2022 | KEN GILL |
| Building Plans Picked Up | 5/16/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 6/10/2022 | GARO TELMI |
| Plan Check Approved | 8/24/2022 | GARO TELMI |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 4/8/2024 | RAMAZANALI ALMASI |
| CofO Issued | 4/17/2024 | ERNESTO CORRAL |
| Permit Finaled | 4/17/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZI | Cleared | 5/19/2022 | DANIEL CORONADO |
| ZI | Cleared | 5/25/2022 | DANIEL CORONADO |
| Historic Resource Verification | Cleared | 5/26/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 6/13/2022 | DAVID URITA |
| Green Code | Cleared | 8/9/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 8/12/2022 | GARO TELMI |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/24/2022 | STEVE MELGAR |
Contact Information
| Architect | , ; Lic. No.: C36534 | 1257 N BRONSON AVENUE LOS ANGELES, CA 90038 |
| Contractor | Western Built Construction Inc; Lic. No.: 951783-B | 8033 SUNSET BLVD #5500 LOS ANGELES, CA 90046 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2023 | Approved | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Approved | JULIAN CAPUCETTI |
| Deputy Reinf. Concrete | 8/8/2023 | Conditional Approval | ALAN MORELOS |
| Deputy Drilled-In Anchors | 8/10/2023 | Conditional Approval | RAFAEL CORTES |
| Deputy Steel/Welding | 8/10/2023 | Conditional Approval | RAFAEL CORTES |
| Deputy Reinf. Concrete | 8/11/2023 | Conditional Approval | RAFAEL CORTES |
| Deputy Reinf. Concrete | 8/14/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Drilled-In Anchors | 8/18/2023 | Conditional Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Reinf. Concrete | 8/23/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Not Ready for Inspection | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Approved | RICARDO ROBLES |
| Pre-Inspection | 10/20/2023 | Partial Approval | VAHE KELEDJIAN |
| Light Gage Steel Frame | 10/26/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 11/6/2023 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 11/7/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 11/8/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 11/15/2023 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 11/17/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 11/20/2023 | Partial Approval | KATY RAMIREZ |
| Interior/Exterior Lathing | 11/21/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Interior/Exterior Lathing | 11/28/2023 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 12/5/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Interior/Exterior Lathing | 12/6/2023 | Approved | RICARDO ROBLES |
| Final | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Green Building Final | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 1/2/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Final | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 2/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 2/13/2024 | Approved | KATY RAMIREZ |
| Final | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 4/3/2024 | No Access for Inspection | RONALD JIMENEZ |
| Footing/Foundation/Slab | 4/3/2024 | No Access for Inspection | RONALD JIMENEZ |
| Green Building Rough | 4/3/2024 | No Access for Inspection | RONALD JIMENEZ |
| Reinforced Masonry Frame | 4/3/2024 | No Access for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 4/3/2024 | No Access for Inspection | RONALD JIMENEZ |
| Final | 4/5/2024 | OK to Issue CofO | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 4/5/2024 | Approved | RAMAZANALI ALMASI |
| Green Building Rough | 4/5/2024 | Approved | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 4/5/2024 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 4/5/2024 | Approved | RAMAZANALI ALMASI |