1553 E VICTORIA AVE 90291
Certificate Information: 1553 E VICTORIA AVE 90291
- Application / Permit
- 22016-10000-10886
- Plan Check / Job No.
- B22LA06271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) DETACHED STORAGE TO (N) ACCESSORY DWELLING UNIT WITH (N) 9'-7" X 9'-1" ADDITION PER GCS 65852.2 (e) (1) (A). ADU TO BE ATTACHED TO (E) DETACHED GARAGE.
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 10/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 4/18/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 10/28/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 11/23/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 12/23/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 1/19/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 1/27/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 10/5/2023 | HERBERT GIRON |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
| CofO Issued | 10/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 6/27/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Reiff,, Brian A; Lic. No.: NA27313 | , |
| Contractor | S K A V Design Inc; Lic. No.: 288619-B | , |
| Engineer | Onishi,, Robert K; Lic. No.: NA3705 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 4/14/2023 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/26/2023 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 4/26/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 4/26/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/2/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/24/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 5/24/2023 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 5/24/2023 | Corrections Issued | HERBERT GIRON |
| Rough-Elec/Plmb/HVAC | 6/23/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 6/26/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 6/26/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/26/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/29/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/29/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/29/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | EVAN COOPER |
| Insulation | 7/6/2023 | Approved | EVAN COOPER |
| Shower Pan | 7/6/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 7/10/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/10/2023 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 7/17/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/15/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/15/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 9/15/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 9/15/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 9/15/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/2/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 10/2/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 10/2/2023 | Approved | HERBERT GIRON |
| Green Building Final | 10/2/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 10/2/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/2/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 10/2/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 10/4/2023 | Approved | HERBERT GIRON |
| Final | 10/4/2023 | OK to Issue CofO | HERBERT GIRON |
| Smoke Detectors | 10/4/2023 | Approved | HERBERT GIRON |