1925 N ST ANDREWS PL 90068
Certificate Information: 1925 N ST ANDREWS PL 90068
- Application / Permit
- 22016-10000-10577
- Plan Check / Job No.
- B22LA06058
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 5'-0" X 12'-0" ADDITION TO THE FRONT OF (E) DETACHED GARAGE AT REAR OF LOT. REMOVE AND REPLACE EXISTING ROOF FRAMING. REPLACE GARAGE DOOR.
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2022 | MINA HABILI |
| Corrections Issued | 4/15/2022 | MINA HABILI |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Applicant returned to address corrections | 6/15/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 6/29/2022 | JOSEPH RAFOLS |
| Issued | 7/12/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 6/6/2023 | DEROLD HAUFF |
| CofO Issued | 6/6/2023 | DEROLD HAUFF |
| Permit Finaled | 6/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 5/19/2022 | LOUIS ORTEGA |
| HPOZ | Cleared | 6/7/2022 | DEEPEAKA DHALIWAL |
| Grading Pre-Inspection | Cleared | 6/10/2022 | KIRK LINKLATER |
| Miscellaneous | Cleared | 6/29/2022 | GEORGE ALVAREZ |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/29/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 8/30/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/1/2022 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 9/7/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/9/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/17/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 11/17/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/6/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/23/2022 | Partial Approval | RUBEN SALAS |
| Interior/Exterior Lathing | 12/23/2022 | Partial Approval | RUBEN SALAS |
| Final | 2/21/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 2/21/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 2/21/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 3/13/2023 | No Access for Inspection | STUART CHAPMAN |
| Final | 3/17/2023 | Conditional Approval | RAUL BARAJAS |
| Final | 3/22/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |