22545 W CLARENDON ST 91367
Certificate Information: 22545 W CLARENDON ST 91367
- Application / Permit
- 22016-10000-10497
- Plan Check / Job No.
- B22LA06044
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISITING DETACHED 2-CAR GARAGE TO NEW ADU PER 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | KHUONG TRUONG |
| Corrections Issued | 4/7/2022 | KHUONG TRUONG |
| Plan Check Approved | 5/18/2022 | FERNANDO FLORES |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 2/27/2023 | TROY SANDERS |
| Permit Finaled | 2/27/2023 | JOHN JANSON |
| CofO Issued | 2/27/2023 | JOHN JANSON |
| Permit Finaled | 2/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/12/2022 | VASIL MIHALEV |
| Address approval | Cleared | 4/13/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/13/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | 7110 FOREST HILLS RD WEST HILLS, CA 91307 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2022 | Approved | ROBERT GOLD |
| Underground Mechanical | 7/25/2022 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 9/30/2022 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 9/30/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | TROY SANDERS |
| Shower Pan | 10/13/2022 | Approved | TROY SANDERS |
| Insulation | 10/19/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 10/24/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | TROY SANDERS |
| Final | 2/23/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 2/23/2023 | Approved | TROY SANDERS |
| Green Building Rough | 2/23/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/23/2023 | Approved | TROY SANDERS |
| Final | 2/27/2023 | OK to Issue CofO | TROY SANDERS |