22545 W CLARENDON ST 91367

Certificate Information: 22545 W CLARENDON ST 91367

Application / Permit
22016-10000-10497
Plan Check / Job No.
B22LA06044
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISITING DETACHED 2-CAR GARAGE TO NEW ADU PER 65852.2(e)(1)(A)
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 2/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Building Plans Picked Up 4/4/2022 APPLICANT
Submitted 4/6/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 KHUONG TRUONG
Corrections Issued 4/7/2022 KHUONG TRUONG
Plan Check Approved 5/18/2022 FERNANDO FLORES
Issued 5/24/2022 APPLICANT
CofO in Progress 2/27/2023 TROY SANDERS
Permit Finaled 2/27/2023 JOHN JANSON
CofO Issued 2/27/2023 JOHN JANSON
Permit Finaled 2/27/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/12/2022 VASIL MIHALEV
Address approval Cleared 4/13/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/13/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/14/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor D K R Construction Inc; Lic. No.: 1070450-B 7110 FOREST HILLS RD      WEST HILLS, CA 91307
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2022 Approved ROBERT GOLD
Underground Mechanical 7/25/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 9/30/2022 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 9/30/2022 Approved TROY SANDERS
Interior/Exterior Lathing 10/13/2022 Partial Approval TROY SANDERS
Shower Pan 10/13/2022 Approved TROY SANDERS
Insulation 10/19/2022 Approved TROY SANDERS
Interior/Exterior Lathing 10/19/2022 Partial Approval TROY SANDERS
Drywall Nailing 10/24/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/23/2023 Approved TROY SANDERS
Final 2/23/2023 Corrections Issued TROY SANDERS
Green Building Final 2/23/2023 Approved TROY SANDERS
Green Building Rough 2/23/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 2/23/2023 Approved TROY SANDERS
Final 2/27/2023 OK to Issue CofO TROY SANDERS