2111 W 67TH ST 90047
Certificate Information: 2111 W 67TH ST 90047
- Application / Permit
- 22016-10000-10483
- Plan Check / Job No.
- B22LA06039
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 12/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | VIVIAN LAO |
| Corrections Issued | 4/8/2022 | VIVIAN LAO |
| Plan Check Approved | 6/8/2022 | VIVIAN LAO |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 12/8/2023 | DAVID FEILER |
| Permit Finaled | 12/12/2023 | DEROLD HAUFF |
| CofO Issued | 12/12/2023 | DEROLD HAUFF |
| Permit Finaled | 12/12/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2022 | CINDY QI |
| Sewer availability | Cleared | 4/15/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | CINDY QI |
| Construction within easement | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/23/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/23/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/6/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/6/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 2/2/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/14/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 3/13/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/20/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/20/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/3/2023 | Approved | JOAQUIN GREENOUGH |
| Sewer | 5/12/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/26/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 6/2/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 6/9/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | ENRIQUE MIRELES |
| Final | 9/1/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/1/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/1/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/8/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 11/28/2023 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/8/2023 | Approved | DAVID FEILER |
| Final | 12/8/2023 | OK to Issue CofO | DAVID FEILER |
| HVAC-Final | 12/8/2023 | Approved | DAVID FEILER |