2610 3/4 S 7TH AVE 90018
Certificate Information: 2610 3/4 S 7TH AVE 90018
- Application / Permit
- 22016-10000-10314
- Plan Check / Job No.
- B22LA05925
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO NEW ACCESSORY DWELLING UNIT AND NEW FRAMED AWNING COVER AT ENTRY . REMOVE AND REFRAME EXISTING ROOF FRAMING FOR GABLE ROOF . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 5/8/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Applicant returned to address corrections | 9/27/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 9/27/2022 | GEORGE ALVAREZ |
| No Progress | 9/27/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 10/31/2022 | VICTOR CHEN |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 3/19/2024 | STUART CHAPMAN |
| CofO in Progress | 3/19/2024 | STUART CHAPMAN |
| No Progress | 5/15/2026 | ALIZAH MAYAGOITIA |
| CofO in Progress | 5/15/2026 | ALIZAH MAYAGOITIA |
| CofO Issued | 5/16/2026 | DEROLD HAUFF |
| Permit Finaled | 5/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/29/2022 | CHRISTOPHER ROCHA |
| HPOZ | Cleared | 8/23/2022 | DANIEL MATA |
Contact Information
| Contractor | Golden Crest Construction; Lic. No.: 549728-B | 311 NORTH LA BREA AVENUE INGLEWOOD, CA 90302 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2023 | No Access for Inspection | CALEB MEISTER |
| Pre-Inspection | 2/13/2023 | Partial Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 5/31/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 5/31/2023 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 7/12/2023 | Corrections Issued | CALEB MEISTER |
| Deputy Drilled-In Anchors | 7/19/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 9/27/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/20/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 11/20/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 11/20/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 11/27/2023 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 11/27/2023 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 11/30/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 12/5/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/5/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 12/5/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/5/2023 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 12/5/2023 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 12/8/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 12/12/2023 | Approved | JUSTIN HAWLEY |
| Final | 1/19/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 1/19/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 1/19/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Final | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 3/6/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/15/2024 | Approved | STUART CHAPMAN |
| Final | 3/15/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 3/15/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/15/2024 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 1/6/2026 | Corrections Issued | BRENDAN MORELLI |
| Final | 5/15/2026 | Not Ready for Inspection | JUSTIN HAWLEY |