4511 W COCKERHAM DR 90027
Certificate Information: 4511 W COCKERHAM DR 90027
- Application / Permit
- 22016-10000-10286
- Plan Check / Job No.
- B22LA05907
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED (575 SF) 2-CAR GARAGE INTO ADU 2 OF 2
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2022 | TSE MING HUANG |
| Corrections Issued | 4/18/2022 | TSE MING HUANG |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Applicant returned to address corrections | 5/13/2022 | MINA HABILI |
| Plan Check Approved | 6/6/2022 | JOSEPH RAFOLS |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 9/20/2022 | JOSEPH MCGARRY |
| CofO Issued | 9/22/2022 | RONALD MYRICK |
| Permit Finaled | 9/22/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Historic monument | Cleared | 4/27/2022 | MELISSA JONES |
| Sewer availability | Cleared | 4/29/2022 | CELINA MORENO |
| Address approval | Cleared | 5/2/2022 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 5/3/2022 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | CELINA MORENO |
| Construction near power lines | Cleared | 5/26/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/26/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Good Form Corporation; Lic. No.: 942151-B | 1920 HILLHURST AVE #V927 LOS ANGELES, CA 90027 |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 3332 BENNETT DRIVE LOS ANGELES, CA 90068 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/22/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/26/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/26/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/26/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/26/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 7/26/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/3/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 8/3/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/3/2022 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 8/3/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 8/5/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/9/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/9/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/16/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | JOSEPH MCGARRY |