4216 W VIRGINIA AVE 90029
Certificate Information: 4216 W VIRGINIA AVE 90029
- Application / Permit
- 22016-10000-10263
- Plan Check / Job No.
- B22LA05877
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) SFD UNIT AND ATTACHED GARAGE AT REAR LOT TO ADU PER STATE LAW PER WFPP
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2022 | ADAM HEGAZI |
| Corrections Issued | 4/13/2022 | ADAM HEGAZI |
| Applicant returned to address corrections | 8/12/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/21/2022 | FERNANDO FLORES |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | FREDDIE RIVERA |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
| CofO Issued | 10/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 8/16/2022 | LOUIS ORTEGA |
| Address approval | Cleared | 8/18/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/18/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 8/25/2022 | ROBERT HUGHES |
| Tenant Habitability Plan | Cleared | 9/20/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/2/2022 | Partial Approval | JOSE AVILA |
| Pre-Inspection | 11/9/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/8/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/11/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/11/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 1/11/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/11/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/11/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/11/2023 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 7/11/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 7/11/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/28/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/28/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | FREDDIE RIVERA |
| Insulation | 8/2/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/8/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/8/2023 | Approved | FREDDIE RIVERA |
| Final | 9/15/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 9/15/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/15/2023 | Approved | FREDDIE RIVERA |
| Final | 10/2/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 10/2/2023 | Approved | FREDDIE RIVERA |