3065 W 8TH ST 90005
Certificate Information: 3065 W 8TH ST 90005
- Application / Permit
- 22016-10000-10032
- Plan Check / Job No.
- B22LA05713
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE USE TO (2) TENANT SPACES TO 1,540 SF RESTAURANT [with two dining rooms]. TOTAL OCCUPANT LOAD 51 . HOURS OF OPERATION 10 AM TO 8 PM.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2022 | JESSE JIMENEZ |
| Corrections Issued | 4/12/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | ADAM HEGAZI |
| Plan Check Approved | 6/10/2022 | ZAW HAN |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | KATY RAMIREZ |
| CofO Issued | 4/12/2023 | ERNESTO CORRAL |
| Permit Finaled | 4/12/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Food establishment approval | Cleared | 4/26/2022 | LACDHS APPROVED |
| Comm Cor/Mini-Mall | Cleared | 5/10/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/10/2022 | LOUIS ORTEGA |
| Redevelopment Project Area | Cleared | 5/17/2022 | SUSAN WONG |
| Food Service Establishment | Cleared | 6/7/2022 | KENNETH BROWNE |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 6/9/2022 | ABEL CASILLAS |
Contact Information
| Contractor | 1 Design Construction Corp; Lic. No.: 929941-B | 2511 BEVERLY BLVD LOS ANGELES, CA 90057 |
| Engineer | Lee,, Sang Wook; Lic. No.: C56699 | 4664 W MAPLEWOOD AVE #305 LOS ANGELES, CA 90004 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2022 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 7/6/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 7/18/2022 | Conditional Approval | NICK DANERI |
| Pre-Inspection | 7/18/2022 | Partial Inspection | NICK DANERI |
| Wood Frame | 7/18/2022 | Partial Approval | NICK DANERI |
| Drywall Nailing | 8/3/2022 | Conditional Approval | DARRYL ARNOLD |
| T-Bar Ceiling | 10/11/2022 | Approved | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 10/31/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 1/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 1/27/2023 | Corrections Issued | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Final | 2/13/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 2/16/2023 | Corrections Issued | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 2/16/2023 | Approved | KATY RAMIREZ |
| Final | 3/15/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | KATY RAMIREZ |
| Final | 4/11/2023 | OK to Issue CofO | KATY RAMIREZ |