1926 W 54TH ST 90062

Certificate Information: 1926 W 54TH ST 90062

Application / Permit
22016-10000-09931
Plan Check / Job No.
B22LA05646
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERSION & ADDITION OF (E) GARAGE & STORAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 9/2/2022
Issuing Office
Current Status
Issued on 9/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 LAMAR DAVIS
Corrections Issued 5/16/2022 LAMAR DAVIS
Quality Review Completed 5/20/2022 SAI KHUM
Applicant returned to address corrections 6/22/2022 LAMAR DAVIS
Plan Check Approved 8/2/2022 LAMAR DAVIS
Issued 9/2/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/1/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 6/2/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/7/2022 WALLIE JONG
Sewer availability Cleared 6/7/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2022 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 10/4/2022 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/31/2022 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/29/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/28/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 12/28/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/30/2022 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 1/3/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 1/3/2023 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 1/6/2023 Approved SABAS ALONSO
Pre-Inspection 2/24/2023 Partial Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 11/27/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 5/8/2025 Corrections Issued BARRY HACHE
Underground Mechanical 5/8/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 7/9/2025 Approved BARRY HACHE
HVAC-Rough 7/9/2025 Corrections Issued BARRY HACHE
MERV13>=Rough 8/6/2025 Not Ready for Inspection BARRY HACHE
Rough-Elec/Plmb/HVAC 8/6/2025 Corrections Issued BARRY HACHE
Sewer 8/6/2025 Approved BARRY HACHE
PLUMBING-Rough 8/28/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 9/9/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 9/9/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 10/22/2025 Corrections Issued BARRY HACHE
Green Building Rough 10/22/2025 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 10/22/2025 Approved BARRY HACHE