4939 N MATILIJA AVE 91423
Certificate Information: 4939 N MATILIJA AVE 91423
- Application / Permit
- 22016-10000-09915
- Plan Check / Job No.
- B22LA05634
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage into ADU
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Corrected on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | JOE VO |
| Corrections Issued | 4/3/2022 | JOE VO |
| Plan Check Approved | 4/8/2022 | JOE VO |
| Issued | 4/19/2022 | APPLICANT |
| CofO in Progress | 11/23/2022 | MISAEL ESPARZA |
| CofO Issued-Status Void | 11/30/2022 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 11/30/2022 | DANIEL ORRANTE |
| Re-Activate Permit | 1/4/2023 | DANIEL ORRANTE |
| CofO Corrected | 4/26/2023 | MICHAEL SMITH |
| Permit Finaled | 4/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/6/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2022 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 6/28/2022 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 7/1/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 7/1/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 7/20/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 7/20/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 7/20/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/25/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/25/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 7/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 7/25/2022 | Approved | MISAEL ESPARZA |
| Insulation | 7/28/2022 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/28/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/2/2022 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 8/8/2022 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/8/2022 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 8/8/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 8/11/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 9/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/21/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 9/29/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 10/31/2022 | Approved | MISAEL ESPARZA |
| Sewer | 10/31/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/10/2022 | Not Ready for Inspection | ROBERT GOLD |
| Final | 11/10/2022 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 11/10/2022 | Approved | ROBERT GOLD |
| HVAC-Final | 11/10/2022 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Final | 11/10/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 11/10/2022 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 11/16/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 11/16/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 11/16/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/22/2022 | Approved | MISAEL ESPARZA |
| Final | 11/22/2022 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 11/22/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 11/22/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | MISAEL ESPARZA |