1513 W SEPULVEDA BLVD 90501
Certificate Information: 1513 W SEPULVEDA BLVD 90501
- Application / Permit
- 22016-10000-09752
- Plan Check / Job No.
- B22LA05511
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- New Tenant improvement of existing retail (admin/storage/break-room/offices) including but not limited to new interior finishes, new interior partitions, electrical, plumbing and HVAC.
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/19/2025
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 4/27/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/5/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/10/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 11/14/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/1/2024 | SERGIO GUTIERREZ |
| Issued | 4/25/2024 | APPLICANT |
| Permit Finaled | 5/16/2025 | JOEY BUCHANAN |
Permit Application Clearance Information
| Green Code | Cleared | 3/17/2023 | SERGIO GUTIERREZ |
| DAS Clearance | Cleared | 6/20/2023 | SERGIO GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | ANA SORIANO |
| Sewer availability | Cleared | 8/17/2023 | ANA SORIANO |
| "Q" conditions | Cleared | 8/21/2023 | KENTON TRINH |
| ZA Case | Cleared | 8/21/2023 | KENTON TRINH |
| ZA Case | Cleared | 8/21/2023 | KENTON TRINH |
Contact Information
| Architect | Oshima,, Brian M; Lic. No.: NA25849 | , |
| Contractor | National Commercial Builders Inc; Lic. No.: 963177-B | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 1/29/2025 | Approved | MICHAEL PETRUSKO |
| T-Bar Ceiling | 3/14/2025 | Approved | MICHAEL PETRUSKO |
| Final | 3/28/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Green Building Final | 3/28/2025 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 3/28/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 4/24/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 4/24/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 5/16/2025 | Permit Finaled | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 5/16/2025 | Approved | JOEY BUCHANAN |