3312 N GLENDALE BLVD 90039

Certificate Information: 3312 N GLENDALE BLVD 90039

Application / Permit
22016-10000-09621
Plan Check / Job No.
B22LA05422
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
CHANGE OF USE FROM OFFICE TO MEDICAL OFFICE. TENANT IMPROVEMENT WORK.
Permit Issued
Issued on 10/28/2022
Issuing Office
Current Status
CofO Issued on 11/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 3/30/2022 JOE VO
Corrections Issued 3/31/2022 JOE VO
Applicant returned to address corrections 4/12/2022 JOE VO
Plan Check Approved 4/25/2022 JOE VO
Issued 10/28/2022 APPLICANT
CofO in Progress 11/2/2023 RAFAEL CORTES
CofO Issued 11/6/2023 ERNESTO CORRAL
Permit Finaled 11/6/2023 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 4/19/2022 DANIEL CORONADO
ZI Cleared 4/19/2022 DANIEL CORONADO
ZI Cleared 4/20/2022 NICOLE SANCHEZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/21/2022 CHRISTOPHER ROCHA
Hold Cleared 11/28/2022 MARIA VENDIVIL

Contact Information

Contractor Decor Home Builders; Lic. No.: 749616-B       ,
Contractor Decor Stone Marble & Granite Inc; Lic. No.: 749616-B       ,
Engineer Yenjai,, Seree; Lic. No.: NA73151       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/17/2022 Corrections Issued MARK FERRARI
Pre-Inspection 11/17/2022 Partial Inspection MARK FERRARI
Footing/Foundation/Slab 11/29/2022 Partial Approval MARK FERRARI
Wood Frame 12/19/2022 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 1/20/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 2/10/2023 Approved RAMAZANALI ALMASI
Posting Pre-Inspection 2/28/2023 Approved RAFAEL CORTES
Wood Frame 3/20/2023 Approved RAFAEL CORTES
Pre-Inspection 3/23/2023 Corrections Issued RAFAEL CORTES
Insulation 3/28/2023 Approved RAFAEL CORTES
Drywall Nailing 4/10/2023 Approved RAFAEL CORTES
Final 8/25/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 8/25/2023 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 10/6/2023 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/20/2023 Partial Inspection RONALD JIMENEZ
Final 10/27/2023 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 10/27/2023 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 10/30/2023 Approved RAMAZANALI ALMASI
Final 10/31/2023 Conditional Approval RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved RAFAEL CORTES
Smoke Detectors 10/31/2023 Approved RAFAEL CORTES
Final 11/2/2023 OK to Issue CofO RAFAEL CORTES