5273 N ELLENWOOD DR 90041

Certificate Information: 5273 N ELLENWOOD DR 90041

Application / Permit
22016-10000-09605
Plan Check / Job No.
B22LA05412
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTERIOR AND INTERIOR REMODEL TO (E) 1-STORY SFD: REMODEL AND BATH ADDITION.
Permit Issued
Issued on 9/23/2022
Issuing Office
Metro
Current Status
Permit Finaled on 5/1/2023

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 3/30/2022 MINA HABILI
Corrections Issued 3/30/2022 MINA HABILI
Building Plans Picked Up 3/31/2022 APPLICANT
Applicant returned to address corrections 6/24/2022 KHUONG TRUONG
Plan Check Approved 7/12/2022 CRISTINA SALAZAR
Plan Check Approved 9/23/2022 CRISTINA SALAZAR
Issued 9/23/2022 APPLICANT
Permit Finaled 5/1/2023 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/6/2022 KIRK LINKLATER

Contact Information

Contractor Ace Building And Drywall Construction; Lic. No.: 987371-B 650 S 4TH AVENUE      LA PUENTE, CA 91746
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/8/2023 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 2/8/2023 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 2/8/2023 Corrections Issued BRIAN SULLIVAN
Shower Pan 2/8/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/10/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/10/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 2/10/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/10/2023 Approved CRAIG VAUGHAN
Shower Pan 2/10/2023 Approved CRAIG VAUGHAN
Drywall Nailing 2/16/2023 Approved CHARLES BOGHOSKHAN
Insulation 2/16/2023 Conditional Approval CHARLES BOGHOSKHAN
Interior/Exterior Lathing 2/16/2023 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 4/13/2023 Corrections Issued BRIAN SULLIVAN
Final 4/13/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 4/13/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 4/13/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 5/1/2023 Approved ALIZAH MAYAGOITIA
Final 5/1/2023 Permit Finaled ALIZAH MAYAGOITIA