10029 PINEWOOD AVE 1-6 91042
Certificate Information: 10029 PINEWOOD AVE 1-6 91042
- Application / Permit
- 22016-10000-09416
- Plan Check / Job No.
- B22LA05296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT 310 SQFT OF EXISTING 2-CAR GARAGE TO ADU IN A 5-UNIT APARTMENT PER STATE LAW AND GCS 65852.2(e)(1)(c).
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | ZAW HAN |
| Corrections Issued | 4/11/2022 | ZAW HAN |
| Plan Check Approved | 6/6/2022 | ZAW HAN |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 7/11/2025 | ANDREW DORSO |
| Permit Finaled | 7/15/2025 | JEFFREY DURAN |
| CofO Issued | 7/15/2025 | JEFFREY DURAN |
| Permit Finaled | 7/15/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 4/14/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/14/2022 | JOSE DUARTE-DIAZ |
| Tenant Habitability Plan | Cleared | 5/4/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 5/27/2022 | SARAH HOUNSELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 1/12/2023 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 10/31/2023 | Not Ready for Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 5/16/2024 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 5/16/2024 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 6/3/2024 | Not Ready for Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 6/3/2024 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 6/3/2024 | Approved | ANDREW DORSO |
| Insulation | 6/10/2024 | Approved | ANDREW DORSO |
| Wood Frame | 6/10/2024 | Approved | ANDREW DORSO |
| Drywall Nailing | 6/21/2024 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 6/21/2024 | Approved | KENNETH ROBERTS |
| Final | 4/11/2025 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 4/11/2025 | Approved | RAFAEL CORTES |
| Final | 7/11/2025 | OK to Issue CofO | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | ANDREW DORSO |