1312 S WOODRUFF AVE 90024

Certificate Information: 1312 S WOODRUFF AVE 90024

Application / Permit
22016-10000-09344
Plan Check / Job No.
B22LA05247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING DETACHED GARAGE & CARPORT AND ADDITION TO CREATE A DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 1/30/2023
Issuing Office
Metro
Current Status
Issued on 1/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 CARLOS MONTES
Corrections Issued 4/12/2022 CARLOS MONTES
Quality Review Completed 4/13/2022 KEN GILL
Building Plans Picked Up 4/18/2022 APPLICANT
Applicant returned to address corrections 7/27/2022 CARLOS MONTES
Plan Check Approved 1/9/2023 CARLOS MONTES
Issued 1/30/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/8/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/8/2022 ANTHONY MAINEZ
Sewer availability Cleared 7/8/2022 ANTHONY MAINEZ
Specific Plan Cleared 7/18/2022 VALERIA CEJA
Grading Pre-Inspection Cleared 7/25/2022 KIRK LINKLATER
Construction near power lines Cleared 9/9/2022 RIDWAN HARDY
Low Impact Development Cleared 11/23/2022 CHRIS VONG
GPI Written Notices Cleared 1/9/2023 CARLOS MONTES

Contact Information

Contractor Jass Construction Services; Lic. No.: 982803-B 2355 WESTWOOD BLVD      LOS ANGELES, CA 90064

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 3/17/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 3/22/2023 Conditional Approval STEPHANIE SWANSON
Deputy Steel/Welding 3/23/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/24/2023 Conditional Approval STEPHANIE SWANSON
Deputy Steel/Welding 3/28/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 3/29/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 9/5/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 9/13/2024 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Conditional Approval STEPHANIE SWANSON
ELECTRICAL-Rough 12/4/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/4/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 1/9/2025 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 1/9/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 1/9/2025 Approved BOBBY KEY
ELECTRICAL-Rough 1/15/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 2/21/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 2/21/2025 Approved STEPHANIE SWANSON
HVAC-Rough 2/21/2025 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/25/2025 Approved STEPHANIE SWANSON
HVAC-Rough 3/25/2025 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 3/28/2025 Approved BOBBY KEY
Insulation 3/28/2025 Corrections Issued BOBBY KEY
HVAC-Rough 5/22/2025 Approved DANIEL VERA
Interior/Exterior Lathing 5/22/2025 Approved DANIEL VERA
Drywall Nailing 6/2/2025 Approved CARLOS MATAMOROS
Service/Power Release 6/2/2025 Corrections Issued CARLOS MATAMOROS
Shower Pan 6/12/2025 Approved DANIEL VERA
Service/Power Release 8/1/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 9/15/2025 Approved DANIEL VERA
ELECTRICAL-Final 9/29/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 10/9/2025 Approved DANIEL VERA
PLUMBING-Final 10/9/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 3/2/2026 Corrections Issued RYAN SALAZAR
PLUMBING-Final 3/2/2026 Approved RYAN SALAZAR