2460 E 12TH ST B 90021

Certificate Information: 2460 E 12TH ST B 90021

Application / Permit
22016-10000-09099
Plan Check / Job No.
B22LA05089
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Eplan. Tenant improvement to an (E) warehouse and office building, including new offices, conference rooms, breakroom, restrooms and stairways at first floor and mezzanine. New HVAC units at rooftop and remove (E) skylights.
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
Permit Finaled on 11/3/2022

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 DANIEL YIP
Corrections Issued 4/28/2022 HELEN NGUYEN
Quality Review Completed 5/11/2022 MICHAEL PEREZ
Plan Check Approved 7/8/2022 DANIEL YIP
Applicant returned to address corrections 7/11/2022 DANIEL YIP
No Progress 7/21/2022 DANIEL YIP
Plan Check Approved 7/21/2022 DANIEL YIP
Issued 7/27/2022 APPLICANT
Permit Finaled 11/2/2022 GREGORY POMISH

Permit Application Clearance Information

DAS Clearance Cleared 6/14/2022 Hernan Arreola
Green Code Cleared 6/22/2022 AARON COSTA

Contact Information

Architect Dwyer,, Mark Steven; Lic. No.: C23283 PO BOX 1392      WRIGHTWOOD, CA 92397
Contractor Elite Construction And Manufacturing Inc; Lic. No.: 1012774-B 5402 OCEANUS DRIVE      HUNTINGTON BEACH, CA 92649
Engineer Rosepink,, Dustin Keith; Lic. No.: S5885 24255 VIA MADRUGADA      MISSION VIEJO, CA 92692

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/12/2022 Approved MARK FERRARI
Deputy Drilled-In Anchors 8/15/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/16/2022 Approved MARK FERRARI
Drywall Nailing 8/23/2022 Partial Approval MARK FERRARI
Drywall Nailing 9/6/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/7/2022 Approved MARK FERRARI
Wood Frame 9/9/2022 Approved MARK FERRARI
Deputy Drilled-In Anchors 9/12/2022 Conditional Approval MARK FERRARI
Drywall Nailing 9/12/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/14/2022 Corrections Issued MARK FERRARI
Wood Frame 9/19/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/26/2022 Partial Approval RUSSELL BONVOULOIR
Wood Frame 9/28/2022 Corrections Issued MARK FERRARI
Drywall Nailing 9/30/2022 Conditional Approval MARK FERRARI
Wood Frame 10/6/2022 Approved MARK FERRARI
Wood Frame 10/7/2022 Partial Inspection RAFAEL ESPINOZA
Final 10/21/2022 Conditional Approval GREGORY POMISH
Green Building Final 10/21/2022 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Approved GREGORY POMISH
Smoke Detectors 10/21/2022 Approved GREGORY POMISH
Final 11/2/2022 Permit Finaled GREGORY POMISH