855 S WINDSOR BLVD 90005
Certificate Information: 855 S WINDSOR BLVD 90005
- Application / Permit
- 22016-10000-08902
- Plan Check / Job No.
- B22LA04980
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING EXISTING 3-BAY ORDINARY MOMENT FRAMES. PROVIDE NEW PLYWOOD SHEATHING TO TO UNDERSIDE OF FLOOR FOR SHEAR TRANSFER
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Current Status
- CofC Issued on 1/24/2023
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2022 | VARAND SARKISIAN |
| Corrections Issued | 4/13/2022 | VARAND SARKISIAN |
| Quality Review Completed | 4/15/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/6/2022 | VARAND SARKISIAN |
| Plan Check Approved | 8/18/2022 | VARAND SARKISIAN |
| Issued | 10/17/2022 | APPLICANT |
| OK for CofC | 1/24/2023 | VAHE KELEDJIAN |
| CofC Issued | 1/24/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| HPOZ | Cleared | 6/29/2022 | AMANDA KAINER |
| Tenant Habitability Plan | Cleared | 10/17/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | One Structural Inc; Lic. No.: 1003868-B | , |
| Contractor | Retrofit 1; Lic. No.: 1003868-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 10/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 10/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/31/2022 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 11/4/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/4/2022 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/23/2022 | Approved | DARRYL ARNOLD |
| Final | 12/8/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/8/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/21/2022 | Not Ready for Inspection | VAHE KELEDJIAN |
| Smoke Detectors | 12/21/2022 | Approved | VAHE KELEDJIAN |
| Final | 1/24/2023 | OK for CofC | VAHE KELEDJIAN |