4000 S NICOLET AVE 90008

Certificate Information: 4000 S NICOLET AVE 90008

Application / Permit
22016-10000-08897
Plan Check / Job No.
B22LA04978
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story Seismic Retrofit per LABC Chapter 93. INSTALL (N)-(7) SPECIAL STEEL CANTILEVERED COLUMNS AND (N)-(1) WOOD SHEAR WALL.
Permit Issued
Issued on 9/23/2022
Issuing Office
Current Status
CofC Issued on 3/13/2023

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 BIDYUT RATH
Corrections Issued 4/18/2022 BIDYUT RATH
Quality Review Completed 4/26/2022 HANS SANTIAGO
Plan Check Approved 7/12/2022 BIDYUT RATH
Issued 9/23/2022 APPLICANT
OK for CofC 2/6/2023 DARRYL ARNOLD
CofC Issued 3/13/2023 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/23/2022 MICHAEL SOTO

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2022 Corrections Issued DARRYL ARNOLD
Footing/Foundation/Slab 12/9/2022 Approved DARRYL ARNOLD
Wood Frame 12/9/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 12/30/2022 Corrections Issued DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 1/10/2023 Corrections Issued DARRYL ARNOLD
Drywall Nailing 1/18/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 1/18/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 1/26/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 1/30/2023 Approved DARRYL ARNOLD
Final 2/6/2023 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 2/6/2023 Approved DARRYL ARNOLD