5663 1/2 W SPOKANE ST 90016
Certificate Information: 5663 1/2 W SPOKANE ST 90016
- Application / Permit
- 22016-10000-08829
- Plan Check / Job No.
- B22LA04937
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO (N) DETACHED ADU Per GCS 65852.2(e)(1)(A) 2 OF 2
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | KHUONG TRUONG |
| Corrections Issued | 4/2/2022 | KHUONG TRUONG |
| Plan Check Approved | 11/4/2022 | FERNANDO FLORES |
| Issued | 12/16/2022 | APPLICANT |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/6/2022 | CELINA MORENO |
| Sewer availability | Cleared | 10/6/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 3/22/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/12/2023 | Approved | STUART CHAPMAN |
| Gas Test | 4/12/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 4/12/2023 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 5/1/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 6/7/2023 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 6/7/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 6/16/2023 | Corrections Issued | JOSE AVILA |
| Insulation | 6/16/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 6/27/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/25/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 9/12/2023 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/6/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/25/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 6/25/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/25/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/14/2024 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 8/14/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 8/14/2024 | Approved | ARTHUR NEGRETE |
| Final | 10/10/2024 | Conditional Approval | ARTHUR NEGRETE |