818 E 118TH ST 90059

Certificate Information: 818 E 118TH ST 90059

Application / Permit
22016-10000-08806
Plan Check / Job No.
B22LA04834
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/3/2022
Issuing Office
Current Status
CofO Issued on 5/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/19/2022 DANIEL YIP
Corrections Issued 3/21/2022 DANIEL YIP
Applicant returned to address corrections 4/23/2022 DANIEL YIP
Applicant returned to address corrections 5/20/2022 DANIEL YIP
Plan Check Approved 8/10/2022 DANIEL YIP
No Progress 8/11/2022 DANIEL YIP
Plan Check Approved 8/11/2022 DANIEL YIP
No Progress 8/12/2022 DANIEL YIP
Plan Check Approved 8/12/2022 DANIEL YIP
No Progress 8/16/2022 DANIEL YIP
Plan Check Approved 8/16/2022 DANIEL YIP
No Progress 8/17/2022 DANIEL YIP
Plan Check Approved 8/17/2022 DANIEL YIP
Plan Check Approved 8/17/2022 JOHN FRANCIA
Plan Check Approved 9/2/2022 JOHN FRANCIA
Issued 9/3/2022 APPLICANT
CofO in Progress 5/22/2023 JOHN KLARIN
CofO Issued 5/22/2023 ANSON MAGLASANG
Permit Finaled 5/22/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/18/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/21/2022 STEVE MELGAR
Sewer availability Cleared 4/25/2022 STEVE MELGAR
Construction near power lines Cleared 7/20/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2022 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 10/28/2022 Corrections Issued JOHN KLARIN
Gas Test 10/28/2022 Approved JOHN KLARIN
Deputy Drilled-In Anchors 11/1/2022 Approved JOHN KLARIN
PLUMBING-Rough 11/10/2022 Partial Approval JOHN KLARIN
Gas Test 11/17/2022 Not Ready for Inspection JOHN KLARIN
Underground Mechanical 11/23/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 12/20/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 12/20/2022 Approved JOHN KLARIN
MERV13>=Rough 12/20/2022 Approved JOHN KLARIN
PLUMBING-Rough 12/20/2022 Approved JOHN KLARIN
Insulation 12/29/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 12/29/2022 Approved JOHN KLARIN
Drywall Nailing 2/3/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 3/3/2023 Approved JOHN KLARIN
Final 5/5/2023 Corrections Issued JOHN KLARIN
MERV13>=Final 5/5/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 5/5/2023 Approved JOHN KLARIN
Final 5/16/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 5/19/2023 Approved JOHN KLARIN
Final 5/19/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 5/19/2023 Approved JOHN KLARIN
PLUMBING-Final 5/19/2023 Approved JOHN KLARIN