520 S GRAND AVE 90071

Certificate Information: 520 S GRAND AVE 90071

Application / Permit
22016-10000-08804
Plan Check / Job No.
B22LA04927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
PROPOSED ROOF TOP EQUIPMENTS INSTALLATION/ANCHORAGE, NEW STRUCTURAL ISOLATION RAIL FOR (2) COOLING TOWERS, INSTALLATION OF PAD FOR FILTRATION SYSTEM, AND ANCHORING OF (2) CHILLERS ON ROOFTOP.
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
Permit Finaled on 12/14/2022

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 ARMEN JIVALAGIAN
Corrections Issued 4/7/2022 ARMEN JIVALAGIAN
Quality Review Completed 4/13/2022 PETER KIM
Building Plans Picked Up 4/19/2022 APPLICANT
Plan Check Approved 6/27/2022 ARMEN JIVALAGIAN
Issued 6/27/2022 APPLICANT
Permit Finaled 12/13/2022 KATY RAMIREZ

Permit Application Clearance Information

"D" conditions Cleared 5/31/2022 DANIEL CORONADO
CPC Cleared 5/31/2022 DANIEL CORONADO
City Hist. Cultural Monument Cleared 5/31/2022 LAMBERT GIESSINGER
Historic monument Cleared 5/31/2022 LAMBERT GIESSINGER
ZA Case Cleared 5/31/2022 DANIEL CORONADO
ZA Case Cleared 5/31/2022 DANIEL CORONADO
ZA Case Cleared 5/31/2022 DANIEL CORONADO
ZI Cleared 6/3/2022 YI LU
Metro Rail approval Cleared 6/9/2022 ARMEN JIVALAGIAN

Contact Information

Contractor Mesa Energy Systems Inc; Lic. No.: 611215-B 2 CROMWELL      IRVINE, CA 92618
Engineer Fong,, Sandy; Lic. No.: C83965 9420 ALTA LAGUNA WAY      SAN DIEGO, CA 92126

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/28/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/29/2022 Approved KATY RAMIREZ
Deputy Reinf. Concrete 6/30/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/18/2022 Conditional Approval WINSTON DUNNING
Structural Steel Frame 9/8/2022 Approved TIMOTHY BUXTON
Final 12/13/2022 Permit Finaled KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 12/13/2022 Approved KATY RAMIREZ