1174 1/2 W 38TH ST 90037

Certificate Information: 1174 1/2 W 38TH ST 90037

Application / Permit
22016-10000-08663
Plan Check / Job No.
B22LA04832
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. Convert existing WORSHOP (280 SF) to ADU PER DETACHED ADU STATE LAW
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 12/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/19/2022 CARLOS MONTES
Corrections Issued 3/21/2022 CARLOS MONTES
Applicant returned to address corrections 4/7/2022 CARLOS MONTES
Applicant returned to address corrections 4/14/2022 CARLOS MONTES
Plan Check Approved 5/14/2022 CARLOS MONTES
Issued 5/17/2022 APPLICANT
CofO in Progress 12/6/2023 SABAS ALONSO
Permit Finaled 12/9/2023 DEROLD HAUFF
CofO Issued 12/9/2023 DEROLD HAUFF
Permit Finaled 12/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/30/2022 MICHAEL SOTO
Address approval Cleared 4/1/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/1/2022 JEANETTE VONG
Sewer availability Cleared 4/1/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/13/2022 No Access for Inspection SABAS ALONSO
Green Building Rough 6/13/2022 No Access for Inspection SABAS ALONSO
PLUMBING-Rough 9/7/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 9/29/2022 Approved SABAS ALONSO
Underground Mechanical 9/29/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/28/2022 Approved SABAS ALONSO
Final 10/28/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 10/28/2022 Approved SABAS ALONSO
Green Building Rough 10/28/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/28/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 12/16/2022 Corrections Issued SABAS ALONSO
Final 12/16/2022 Corrections Issued SABAS ALONSO
HVAC-Final 12/16/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 12/16/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 12/16/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/21/2022 Corrections Issued SABAS ALONSO
Final 12/21/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Final 12/21/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 12/21/2022 Approved SABAS ALONSO
ELECTRICAL-Final 6/8/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 8/15/2023 Corrections Issued SABAS ALONSO
Final 8/15/2023 Corrections Issued SABAS ALONSO
HVAC-Final 8/15/2023 Approved SABAS ALONSO
PLUMBING-Final 8/15/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 8/28/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 8/30/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 9/5/2023 Approved STUART CHAPMAN
Final 10/23/2023 Corrections Issued SABAS ALONSO
Final 11/15/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/5/2023 Approved SABAS ALONSO
Final 12/5/2023 OK to Issue CofO SABAS ALONSO