4465 W 10TH ST 90019

Certificate Information: 4465 W 10TH ST 90019

Application / Permit
22016-10000-08611
Plan Check / Job No.
B22LA04805
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTIC AND PORTION OF GARAGE TO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/10/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/29/2022 SHANGQIN XIE
Corrections Issued 3/30/2022 SHANGQIN XIE
Building Plans Picked Up 3/31/2022 APPLICANT
Plan Check Approved 5/31/2022 FERNANDO FLORES
Issued 11/10/2022 APPLICANT
CofO in Progress 7/5/2024 JEFFREY MEAD
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/18/2022 CINDY QI
Address approval Cleared 5/19/2022 CINDY QI
Construction near power lines Cleared 5/23/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/23/2022 CINDY QI
Sewer availability Cleared 5/23/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Pina,, Paul Cohn; Lic. No.: S4194 2204 TORRANCE BLVD 105A      TORRANCE, CA 90501

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 6/7/2023 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 6/30/2023 Corrections Issued JEFFREY MEAD
HVAC-Rough 6/30/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 6/30/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 7/10/2023 Approved JEFFREY MEAD
HVAC-Rough 7/10/2023 Approved JEFFREY MEAD
PLUMBING-Rough 7/10/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/12/2023 Approved JEFFREY MEAD
METHANE-Rough 7/12/2023 Approved JEFFREY MEAD
Wood Frame 7/12/2023 Approved JEFFREY MEAD
Insulation 7/14/2023 Partial Approval JEFFREY MEAD
Deputy Wood Construction 7/26/2023 Approved DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Approval CHARLES BOGHOSKHAN
Insulation 7/28/2023 Partial Approval CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved JEFFREY MEAD
Insulation 8/4/2023 Approved JEFFREY MEAD
Drywall Nailing 8/16/2023 Approved JOSH MEISTER
Final 6/24/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 6/24/2024 Approved AMIR NAZARIAN
Final 7/1/2024 Corrections Issued AMIR NAZARIAN
Final 7/5/2024 OK to Issue CofO JEFFREY MEAD
Service/Power Release 7/5/2024 Approved JEFFREY MEAD