1516 S ST ANDREWS PL 90019
Certificate Information: 1516 S ST ANDREWS PL 90019
- Application / Permit
- 22016-10000-08572
- Plan Check / Job No.
- B22LA04779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-STORY STORAGE BUILDING TO AN ADU per GCS 65852.2(e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 01/18/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | LUKE GONZALES |
| Corrections Issued | 4/1/2022 | LUKE GONZALES |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | ADAM HEGAZI |
| Plan Check Approved | 4/28/2022 | DANIEL SANJUAN |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 10/23/2023 | WILLIAM MICHALAK |
| Permit Finaled | 10/27/2023 | BRUCE TODD |
| CofO Issued | 10/27/2023 | BRUCE TODD |
| Permit Finaled | 10/27/2023 | BRUCE TODD |
Permit Application Clearance Information
| Construction within easement | Cleared | 4/4/2022 | RIDWAN HARDY |
| Address approval | Cleared | 4/5/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 4/5/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 4/7/2022 | RAFAEL FONTES |
| ZA Case | Cleared | 4/7/2022 | RAFAEL FONTES |
Contact Information
| Architect | Driscoll,, Christopher; Lic. No.: C36073 | 2826 8TH AVE LOS ANGELES, CA 90018 |
| Contractor | Coleman Construction Inc; Lic. No.: 697040-B | 1973 W 48TH STREET LOS ANGELES, CA 90062 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2022 | Approved | WILLIAM MICHALAK |
| Pre-Inspection | 11/8/2022 | Partial Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 5/9/2023 | Partial Approval | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 5/26/2023 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 5/26/2023 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 6/2/2023 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/21/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 6/21/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 6/21/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 6/21/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 6/27/2023 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/11/2023 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | WILLIAM MICHALAK |
| Drywall Nailing | 7/18/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 8/11/2023 | Approved | WILLIAM MICHALAK |
| Final | 8/11/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Final | 8/11/2023 | Approved | WILLIAM MICHALAK |
| METHANE-Final | 8/11/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Final | 8/11/2023 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 8/11/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 8/16/2023 | Approved | GLEN RAND |
| HVAC-Final | 8/16/2023 | Approved | GLEN RAND |
| PLUMBING-Final | 8/16/2023 | Approved | GLEN RAND |
| ELECTRICAL-Final | 9/5/2023 | Approved | WILLIAM MICHALAK |
| Final | 9/5/2023 | Conditional Approval | WILLIAM MICHALAK |
| HVAC-Final | 9/5/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Final | 9/5/2023 | Approved | WILLIAM MICHALAK |