2324 N FLETCHER DR 90039

Certificate Information: 2324 N FLETCHER DR 90039

Application / Permit
22016-10000-08454
Plan Check / Job No.
B22LA04727
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Massage Parlor
Work Description
CHANGE OF USE FROM RETAIL TO MASSAGE PARLOR "WHERE ANY PERSON WHO PROVIDES MASSAGE SERVICES AT THIS PREMISE SHALL BE CERTIFIED AS A MASSAGE THERAPIST OR MASSAGE PRACTITIONER PURSUANT TO CALIFORNIA BUSINESS AND PROFESSIONS SECTION 4600 ET. SEQ.". AND T.I. TO ADD INTERIOR NON-BEARING PARTITION WALLS. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 01/05/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 6/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/29/2022 FERNANDO FLORES
Corrections Issued 3/30/2022 FERNANDO FLORES
Building Plans Picked Up 3/31/2022 APPLICANT
Applicant returned to address corrections 4/20/2022 ZAW HAN
Plan Check Approved 4/21/2022 ZAW HAN
Issued 6/3/2022 APPLICANT
CofO in Progress 9/9/2022 MARK FERRARI
CofO Issued 9/28/2022 TED RIES
Permit Finaled 9/28/2022 TED RIES

Permit Application Clearance Information

"Q" conditions Cleared 4/5/2022 RICHARD REASER
Comm Cor/Mini-Mall Cleared 4/5/2022 RICHARD REASER
Comm Cor/Mini-Mall Cleared 4/5/2022 RICHARD REASER
Comm Cor/Mini-Mall Cleared 4/5/2022 RICHARD REASER
ZA Case Cleared 4/5/2022 RICHARD REASER
Address approval Cleared 4/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/12/2022 CINDY QI
Sewer availability Cleared 4/12/2022 CINDY QI

Contact Information

Contractor Itsara Construction; Lic. No.: 729294-B 3144 ASHLEY WAY      SACRAMENTO, CA 95833

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 6/17/2022 Corrections Issued MARK FERRARI
Wood Frame 7/14/2022 Approved MARK FERRARI
Drywall Nailing 7/18/2022 Not Ready for Inspection ALFREDO BALANDRA
Drywall Nailing 7/19/2022 Approved MARK FERRARI
Final 8/5/2022 Not Ready for Inspection BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Not Ready BRUCE CAMPBELL
Smoke Detectors 8/5/2022 Approved BRUCE CAMPBELL
Final 8/11/2022 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready MARK FERRARI
Final 8/18/2022 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved MARK FERRARI
Final 9/9/2022 Conditional Approval MARK FERRARI