8218 W 3RD ST 90048
Certificate Information: 8218 W 3RD ST 90048
- Application / Permit
- 22016-10000-08323
- Plan Check / Job No.
- B22LA04647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE FROM (E) SALON TO (N) LAW OFFICE. NEW WINDOW AT STORE-FRONT AND RESTRIPING OF PARKING AREA. PARTIAL REMOVAL & REPLACEMENT OF INTERIOR SLAB ON GRADE FOUNDATION
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Current Status
- Permit Closed on 11/26/2024
- Certificate of Occupancy
- Permit Closed More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | LAMAR DAVIS |
| Corrections Issued | 3/31/2022 | LAMAR DAVIS |
| Quality Review Completed | 4/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 4/12/2022 | APPLICANT |
| Applicant returned to address corrections | 5/10/2022 | LAMAR DAVIS |
| Plan Check Approved | 5/16/2022 | LAMAR DAVIS |
| Issued | 6/22/2022 | APPLICANT |
| Permit Closed | 11/26/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 4/18/2022 | KENTON TRINH |
| Encroachment in public way | Cleared | 4/25/2022 | JEREMY CHOK |
| DAS Clearance | Cleared | 5/9/2022 | CHOI YAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | JEANIE LAM |
Contact Information
| Architect | Bruce,, Thomas A; Lic. No.: C31251 | 1837 N WILTON PL 6 LOS ANGELES, CA 90028 |
| Contractor | Parsa Design & Development Inc; Lic. No.: 1047027-B | 17383 W SUNSET BLVD #A340 PACIFIC PALISADES, CA 90272 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Approved | EDWIN GREGORYONA |
| METHANE-Rough | 8/24/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 8/24/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 9/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 9/26/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 9/26/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/6/2023 | Partial Approval | JEROME BLACKWOOD |
| Pre-Inspection | 7/2/2024 | Partial Inspection | JACOB MYERS |
| Final | 8/16/2024 | Conditional Approval | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV No Gas | JACOB MYERS |
| Smoke Detectors | 8/16/2024 | Approved | JACOB MYERS |
| Wood Frame | 8/16/2024 | Approved | JACOB MYERS |
| Final | 10/15/2024 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Final | 11/4/2024 | Conditional Approval | MARTIN TAVITIAN |