1045 N ARDMORE AVE 90029

Certificate Information: 1045 N ARDMORE AVE 90029

Application / Permit
22016-10000-08263
Plan Check / Job No.
B22LA04608
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install new Special Steel Cantilever Columns and wood shear walls. ADU Conversion obtained under separate permit 22016-10000-08231. **Certificate of Compliance for Soft Story shall not be issued till Certificate of Occupancy for ADU Conversion permit is obtained**
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofC Issued on 10/4/2024

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 HANS SANTIAGO
Corrections Issued 3/29/2022 HANS SANTIAGO
Quality Review Completed 3/30/2022 SAI KHUM
Applicant returned to address corrections 4/11/2022 HANS SANTIAGO
Plan Check Approved 4/15/2022 ANDREW SANTIAGO
Issued 6/21/2022 APPLICANT
OK for CofC 10/4/2024 WINSTON DUNNING
CofC Issued 10/4/2024 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/14/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Largo Construction Inc; Lic. No.: 1011935-B       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/25/2022 Not Ready for Inspection DARRYL ARNOLD
Pre-Inspection 11/1/2022 Corrections Issued DARRYL ARNOLD
Special/Order Compliance 11/3/2022 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 11/3/2022 Partial Inspection GREGORY POMISH
Pre-Inspection 2/23/2023 Partial Approval VAHE KELEDJIAN
Excavation/Setback/Form/Re-Bar 5/23/2023 No Access for Inspection VAHE KELEDJIAN
Special/Order Compliance 8/2/2023 Partial Inspection TIMOTHY POWELL
Deputy Wood Construction 8/4/2023 Conditional Approval VAHE KELEDJIAN
Structural Steel Frame 9/6/2023 Partial Inspection VAHE KELEDJIAN
Structural Steel Frame 11/1/2023 Partial Approval JACOB MYERS
Footing/Foundation/Slab 12/8/2023 Approved JACOB MYERS
Final 12/15/2023 Not Ready for Inspection JACOB MYERS
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Not Ready JACOB MYERS
Smoke Detectors 12/15/2023 Not Ready for Inspection JACOB MYERS
Wood Frame 12/19/2023 Not Ready for Inspection JACOB MYERS
Wood Frame 12/21/2023 Partial Approval LUIS CCAMACHO
Wood Frame 12/26/2023 Not Ready for Inspection JACOB MYERS
Wood Frame 12/28/2023 Approved JACOB MYERS
Interior/Exterior Lathing 12/29/2023 Partial Approval JACOB MYERS
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready JACOB MYERS
Smoke Detectors 1/10/2024 Not Ready for Inspection JACOB MYERS
Final 1/18/2024 Not Ready for Inspection JACOB MYERS
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Not Ready JACOB MYERS
Smoke Detectors 1/18/2024 Not Ready for Inspection JACOB MYERS
Final 1/23/2024 Partial Approval JACOB MYERS
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved JACOB MYERS
Smoke Detectors 1/23/2024 Approved JACOB MYERS
Final 10/4/2024 OK for CofC WINSTON DUNNING