8840 W CASHIO ST 90035
Certificate Information: 8840 W CASHIO ST 90035
- Application / Permit
- 22016-10000-08253
- Plan Check / Job No.
- B22LA04598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan Convert existing detached garage to an Accessory Dwelling Unit per ordinance.
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Current Status
- CofO Issued on 10/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/16/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/30/2022 | MICHAEL LOPEZ |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 10/3/2022 | EVAN COOPER |
| Permit Finaled | 10/5/2022 | DANIEL ORRANTE |
| CofO Issued | 10/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/23/2022 | JEANIE LAM |
Contact Information
| Contractor | Inspire Concepts Inc ; Lic. No.: 1037765-B | , |
| Engineer | Boranian,, Paul; Lic. No.: NA5944 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 6/10/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/17/2022 | Approved | EVAN COOPER |
| Sewer | 6/17/2022 | Approved | EVAN COOPER |
| Wood Frame | 6/17/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | EVAN COOPER |
| Green Building Rough | 6/27/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 6/27/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/27/2022 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 6/27/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/27/2022 | Approved | EVAN COOPER |
| Insulation | 7/5/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 7/28/2022 | Approved | EVAN COOPER |
| Final | 9/13/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 9/13/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 9/13/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 10/3/2022 | Approved | EVAN COOPER |
| Final | 10/3/2022 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 10/3/2022 | Approved | EVAN COOPER |
| HVAC-Final | 10/3/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 10/3/2022 | Approved | EVAN COOPER |