2999 S OVERLAND AVE 90064
Certificate Information: 2999 S OVERLAND AVE 90064
- Application / Permit
- 22016-10000-08224
- Plan Check / Job No.
- B22LA04578
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePLAN. Modify an existing wireless installation. Remove and replace (9) existing panel antennas with (9) new panel antennas at existing rooftop . Remove (6) Existing RRUs-12 at existing penthouse .Remove (3) Existing RRUs-32 B66 at existing penthouse . Remove (3) Existing DC2 surge suppressors at existing penthouse. Remove (1) Existing BBU 5216 at existing equipment location . Relocated (3) Existing RRUs-E2 B29 from existing building rooftop . Install (3) New RRUs-8843 B2/B66A at existing rooftop.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/30/2023
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | KEVIN MORALES |
| Corrections Issued | 5/13/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 7/4/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 7/6/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 7/14/2022 | KEVIN MORALES |
| Plan Check Approved | 7/27/2022 | SELLA BENYAMIN |
| Issued | 8/19/2022 | APPLICANT |
| Permit Finaled | 6/30/2023 | FARHAD DADBIN |
Permit Application Clearance Information
| Plan Approval | Cleared | 7/25/2022 | SANTOS SANCHEZ |
| ZA Case | Cleared | 7/25/2022 | SANTOS SANCHEZ |
| ZA Case | Cleared | 7/25/2022 | SANTOS SANCHEZ |
| ZA Case | Cleared | 7/25/2022 | SANTOS SANCHEZ |
Contact Information
| Contractor | Bechtel Infrastructure And Power Corporation; Lic. No.: 913045-B | , |
| Engineer | Lee,, Chris S; Lic. No.: C76549 | 400 S NORTON AVE A LOS ANGELES, CA 90020 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/30/2023 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV No Gas | FARHAD DADBIN |
| Smoke Detectors | 6/30/2023 | Approved | FARHAD DADBIN |