1341 N LUCILE AVE 90026

Certificate Information: 1341 N LUCILE AVE 90026

Application / Permit
22016-10000-07357
Plan Check / Job No.
B22LA04475
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE IN TO ADU PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 8/31/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/23/2022 FERNANDO FLORES
Corrections Issued 3/24/2022 FERNANDO FLORES
Plan Check Approved 4/28/2022 RAHEL BEYENE
Building Plans Picked Up 5/13/2022 APPLICANT
Issued 8/31/2022 APPLICANT
CofO in Progress 12/22/2022 MICHAEL LEWIS
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/1/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/1/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/14/2022 CHRISTOPHER ROCHA

Contact Information

Architect Sabikhi,, Sidhartha; Lic. No.: C32564 933 MICHELTORENA ST      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/12/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 10/11/2022 Approved FREDDIE RIVERA
HVAC-Rough 10/11/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 10/11/2022 Partial Approval FREDDIE RIVERA
Sewer 10/11/2022 Approved FREDDIE RIVERA
Underground Mechanical 10/11/2022 Partial Approval FREDDIE RIVERA
Wood Frame 10/11/2022 Approved FREDDIE RIVERA
Insulation 10/19/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 10/19/2022 Approved FREDDIE RIVERA
Shower Pan 10/19/2022 Approved FREDDIE RIVERA
Special/Order Compliance 10/19/2022 Corrections Issued FREDDIE RIVERA
Underground Mechanical 10/19/2022 Partial Approval FREDDIE RIVERA
Drywall Nailing 10/24/2022 Approved FREDDIE RIVERA
Insulation 10/24/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/28/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/15/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 12/15/2022 Approved FREDDIE RIVERA
Final 12/15/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 12/15/2022 Approved FREDDIE RIVERA
Green Building Rough 12/15/2022 Approved FREDDIE RIVERA
HVAC-Final 12/15/2022 Approved FREDDIE RIVERA
PLUMBING-Final 12/15/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 12/15/2022 Approved FREDDIE RIVERA
Final 12/21/2022 OK to Issue CofO MICHAEL LEWIS