4700 N FARMDALE AVE 91602
Certificate Information: 4700 N FARMDALE AVE 91602
- Application / Permit
- 22016-10000-07304
- Plan Check / Job No.
- B22LA04454
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INTERIOR ALTERATION TO EXISTING 1-STORY SINGLE FAMILY RESIDENCE. BATHROOM AND KITCHEN REMODEL (NO CHANGE IN FLOOR AREA, HEIGHT, USE)
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/26/2022
Permit Application Status History
| Submitted | 3/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | RACHEL BEYENE |
| Corrections Issued | 3/18/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 4/3/2022 | AUNG SOE |
| Plan Check Approved | 4/6/2022 | AUNG SOE |
| Issued | 4/29/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Permit Finaled | 10/25/2022 | JACK KARGODORIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Proact Construction; Lic. No.: 904819-B | 5739 KANAN ROAD #201 AGOURA HILLS, CA 91301 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/5/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/11/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/9/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/9/2022 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Rough | 6/9/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 6/9/2022 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 6/14/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/15/2022 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/15/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/21/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/21/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 6/29/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/29/2022 | Approved | HERBERT GIRON |
| Final | 10/18/2022 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Final | 10/18/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/18/2022 | Approved | JACK KARGODORIAN |
| Final | 10/25/2022 | Permit Finaled | JACK KARGODORIAN |