1708 S CENTINELA AVE 90025
Certificate Information: 1708 S CENTINELA AVE 90025
- Application / Permit
- 22016-10000-07165
- Plan Check / Job No.
- B22LA04368
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage 21'x19' two-car garage to Accessory Dwelling Unit (ADU)
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 3/23/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/1/2022 | JOE VO |
| Issued | 5/5/2022 | APPLICANT |
| CofO in Progress | 8/4/2024 | KIRK SANDERS |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
| CofO Issued | 8/26/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2022 | JENSON LEE |
| Sewer availability | Cleared | 3/31/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | JENSON LEE |
| Specific Plan | Cleared | 4/12/2022 | VALERIA CEJA |
Contact Information
| Contractor | Ec King Development Corporation; Lic. No.: 1039047-B | 10175 LAUREL CANYON BLVD PACOIMA, CA 91331 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/23/2022 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 7/5/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/3/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/3/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/3/2022 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 8/3/2022 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/27/2022 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 9/27/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 4/6/2023 | Partial Approval | CLAYTON GRAHAM |
| Wood Frame | 5/12/2023 | Corrections Issued | EVAN COOPER |
| Insulation | 5/25/2023 | Corrections Issued | JESUS PINEDA |
| Insulation | 5/31/2023 | Conditional Approval | JESUS PINEDA |
| Drywall Nailing | 6/26/2023 | Approved | JESUS PINEDA |
| Shower Pan | 7/7/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 12/14/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 12/14/2023 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/29/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 3/29/2024 | Approved | JESUS PINEDA |
| Final | 3/29/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 3/29/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 3/29/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 3/29/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 3/29/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/7/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 6/7/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | KIRK SANDERS |
| Final | 8/2/2024 | OK to Issue CofO | KIRK SANDERS |
| Footing/Foundation/Slab | 8/2/2024 | Approved | KIRK SANDERS |