1729 1/2 W 255TH ST 90717

Certificate Information: 1729 1/2 W 255TH ST 90717

Application / Permit
22016-10000-07030
Plan Check / Job No.
B22LA04288
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to an ADU
Permit Issued
Issued on 5/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2022 APPLICANT
Assigned to Plan Check Engineer 4/5/2022 JOSEPH RAFOLS
Corrections Issued 4/6/2022 JOSEPH RAFOLS
Building Plans Picked Up 4/11/2022 APPLICANT
Plan Check Approved 5/6/2022 ADAM HEGAZI
Issued 5/13/2022 APPLICANT
CofO in Progress 8/17/2023 EUGENE CASSIDY
CofO Issued 8/17/2023 ANSON MAGLASANG
Permit Finaled 8/17/2023 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 4/15/2022 WALTER RAMIREZ
Tenant Habitability Plan Cleared 4/18/2022 MICHAEL SOTO
Sewer availability Cleared 4/19/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 4/29/2022 JOSE HERNANDEZ
Address approval Cleared 5/4/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/18/2022 Partial Inspection EUGENE CASSIDY
Footing/Foundation/Slab 7/12/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 9/14/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 11/18/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 12/9/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 12/22/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/10/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 2/10/2023 Approved EUGENE CASSIDY
Insulation 3/7/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/7/2023 Partial Approval EUGENE CASSIDY
Insulation 3/20/2023 Approved EUGENE CASSIDY
Drywall Nailing 3/30/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 4/11/2023 Approved EUGENE CASSIDY
Drywall Nailing 4/11/2023 Approved EUGENE CASSIDY
Final 6/30/2023 Corrections Issued EUGENE CASSIDY
Smoke Detectors 6/30/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/6/2023 Approved EUGENE CASSIDY
Final 7/6/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 7/6/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/6/2023 Approved EUGENE CASSIDY
Smoke Detectors 7/6/2023 Approved EUGENE CASSIDY