7425 S NAYLOR AVE 90045

Certificate Information: 7425 S NAYLOR AVE 90045

Application / Permit
22016-10000-06926
Plan Check / Job No.
B22LA04222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing accessory building (garage) into detached ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 11/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 ARSALAN SHABESTARI
Corrections Issued 3/10/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 4/7/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 4/12/2022 ARSALAN SHABESTARI
Plan Check Approved 5/27/2022 ARSALAN SHABESTARI
Issued 6/16/2022 APPLICANT
CofO in Progress 11/2/2022 BOBBY KEY
Permit Finaled 11/3/2022 DANIEL ORRANTE
CofO Issued 11/3/2022 DANIEL ORRANTE
Permit Finaled 11/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/24/2022 SERGIO VALENZUELA
Address approval Cleared 3/31/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/31/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/4/2022 HISASHI KOBAYAKAWA
Construction near power lines Cleared 5/25/2022 TINA MIRANDA
Construction within easement Cleared 5/25/2022 TINA MIRANDA

Contact Information

Contractor Everlast Home Builders Inc; Lic. No.: 910398-B 11054 VENTURA BLVD #321      STUDIO CITY, CA 91604

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/21/2022 Approved BOBBY KEY
ELECTRICAL-Rough 7/13/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 7/13/2022 Not Ready for Inspection HERBERT GIRON
Sewer 7/13/2022 Approved HERBERT GIRON
Underground Mechanical 7/13/2022 Approved HERBERT GIRON
Footing/Foundation/Slab 7/18/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 7/20/2022 Approved HERBERT GIRON
Insulation 8/8/2022 Corrections Issued BOBBY KEY
Insulation 8/10/2022 Partial Approval BOBBY KEY
ELECTRICAL-Final 8/29/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 8/29/2022 Approved BOBBY KEY
HVAC-Final 8/29/2022 Corrections Issued BOBBY KEY
HVAC-Rough 8/29/2022 Approved BOBBY KEY
PLUMBING-Rough 8/29/2022 Approved BOBBY KEY
Deputy Wood Construction 9/1/2022 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 9/2/2022 Approved BOBBY KEY
Green Building Rough 9/2/2022 Approved BOBBY KEY
Interior/Exterior Lathing 9/2/2022 Partial Approval BOBBY KEY
Shower Pan 9/2/2022 Approved BOBBY KEY
Insulation 9/7/2022 Approved BOBBY KEY
Interior/Exterior Lathing 9/7/2022 Approved BOBBY KEY
Drywall Nailing 9/9/2022 Approved BOBBY KEY
Final 9/9/2022 Corrections Issued BOBBY KEY
Green Building Final 9/15/2022 Partial Approval BOBBY KEY
Interior/Exterior Lathing 9/23/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/24/2022 Corrections Issued BOBBY KEY
HVAC-Final 10/24/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 10/24/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 10/24/2022 Approved BOBBY KEY
ELECTRICAL-Final 11/1/2022 Approved BOBBY KEY
Final 11/1/2022 OK to Issue CofO BOBBY KEY
Green Building Final 11/1/2022 Approved BOBBY KEY
HVAC-Final 11/1/2022 Approved BOBBY KEY
PLUMBING-Final 11/1/2022 Approved BOBBY KEY