5426 1/2 S 5TH AVE 90043
Certificate Information: 5426 1/2 S 5TH AVE 90043
- Application / Permit
- 22016-10000-06847
- Plan Check / Job No.
- B22LA04169
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | CARLOS MONTES |
| Corrections Issued | 4/2/2022 | CARLOS MONTES |
| Quality Review Completed | 4/13/2022 | KEN GILL |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| Applicant returned to address corrections | 7/13/2022 | CARLOS MONTES |
| Plan Check Approved | 7/13/2022 | CARLOS MONTES |
| Issued | 7/18/2022 | APPLICANT |
| CofO in Progress | 7/26/2024 | ANTHONY EGSON |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
| CofO Issued | 9/3/2024 | RUBEN SALAS |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | CINDY QI |
| Sewer availability | Cleared | 6/9/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/9/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 5/12/2023 | Approved | ANTHONY EGSON |
| Underground Mechanical | 5/12/2023 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/24/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/26/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/8/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/15/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/18/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/1/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 9/1/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/19/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/12/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/12/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/13/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 11/20/2023 | Approved | ANTHONY EGSON |
| Insulation | 11/20/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Corrections Issued | ANTHONY EGSON |
| Special/Order Compliance | 12/4/2023 | Partial Inspection | ANTHONY EGSON |
| Special/Order Compliance | 12/4/2023 | Partial Inspection | DAVID FEILER |
| Deputy Wood Construction | 1/23/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 1/25/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/30/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/15/2024 | Approved | BRENDAN MORELLI |
| Final | 5/29/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/29/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV No Gas | ANTHONY EGSON |
| Smoke Detectors | 5/29/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/27/2024 | Approved | ANTHONY EGSON |
| Final | 7/1/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/1/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 7/25/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 7/25/2024 | Approved | ANTHONY EGSON |