5426 1/2 S 5TH AVE 90043

Certificate Information: 5426 1/2 S 5TH AVE 90043

Application / Permit
22016-10000-06847
Plan Check / Job No.
B22LA04169
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 7/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CARLOS MONTES
Corrections Issued 4/2/2022 CARLOS MONTES
Quality Review Completed 4/13/2022 KEN GILL
Building Plans Picked Up 6/3/2022 APPLICANT
Applicant returned to address corrections 7/13/2022 CARLOS MONTES
Plan Check Approved 7/13/2022 CARLOS MONTES
Issued 7/18/2022 APPLICANT
CofO in Progress 7/26/2024 ANTHONY EGSON
Permit Finaled 9/3/2024 RUBEN SALAS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/9/2022 CINDY QI
Sewer availability Cleared 6/9/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/13/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/9/2023 Corrections Issued ANTHONY EGSON
Sewer 5/12/2023 Approved ANTHONY EGSON
Underground Mechanical 5/12/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 5/24/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/26/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 6/8/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 6/15/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/18/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 9/1/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 9/1/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 9/1/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 9/1/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 9/19/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/12/2023 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/12/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 11/2/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval ANTHONY EGSON
Green Building Rough 11/2/2023 Approved ANTHONY EGSON
HVAC-Rough 11/2/2023 Approved ANTHONY EGSON
PLUMBING-Rough 11/2/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/13/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/20/2023 Approved ANTHONY EGSON
Green Building Rough 11/20/2023 Approved ANTHONY EGSON
Insulation 11/20/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Corrections Issued ANTHONY EGSON
Special/Order Compliance 12/4/2023 Partial Inspection ANTHONY EGSON
Special/Order Compliance 12/4/2023 Partial Inspection DAVID FEILER
Deputy Wood Construction 1/23/2024 Approved ANTHONY EGSON
Wood Frame 1/25/2024 Approved ANTHONY EGSON
Drywall Nailing 1/30/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/30/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 2/15/2024 Approved BRENDAN MORELLI
Final 5/29/2024 Corrections Issued ANTHONY EGSON
Green Building Final 5/29/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV No Gas ANTHONY EGSON
Smoke Detectors 5/29/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 6/27/2024 Approved ANTHONY EGSON
Final 7/1/2024 Corrections Issued ANTHONY EGSON
Green Building Final 7/1/2024 Not Ready for Inspection ANTHONY EGSON
Final 7/25/2024 OK to Issue CofO ANTHONY EGSON
Green Building Final 7/25/2024 Approved ANTHONY EGSON