4830-4832 E BUCHANAN ST 90042

Certificate Information: 4830-4832 E BUCHANAN ST 90042

Application / Permit
22016-10000-06724
Plan Check / Job No.
B22LA04124
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached basement garage into an ATTACHED ADU PER STATE LAW
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 1/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 CARLOS MONTES
Corrections Issued 3/10/2022 CARLOS MONTES
Plan Check Approved 4/26/2022 CARLOS MONTES
Issued 4/27/2022 APPLICANT
CofO in Progress 1/25/2023 CRAIG VAUGHAN
CofO Issued 1/27/2023 DEROLD HAUFF
Permit Finaled 1/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/22/2022 JEANETTE VONG
Sewer availability Cleared 3/22/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/23/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2022 No Access for Inspection CRAIG VAUGHAN
Pre-Inspection 5/4/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/8/2022 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 7/14/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 7/21/2022 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/21/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/1/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 9/1/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 9/1/2022 Corrections Issued CRAIG VAUGHAN
Drywall Nailing 9/9/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/9/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/21/2022 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 9/27/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 11/9/2022 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 11/9/2022 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/9/2022 Approved CRAIG VAUGHAN
HVAC-Rough 11/16/2022 Approved SCOTT FINNILA
Interior/Exterior Lathing 11/16/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 12/20/2022 Corrections Issued HAMIK HARTOUNIAN
Final 12/20/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 12/20/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/3/2023 Approved BRIAN SULLIVAN
Final 1/3/2023 Corrections Issued BRIAN SULLIVAN
Final 1/24/2023 OK to Issue CofO CRAIG VAUGHAN