6133 W BARROWS DR 90048

Certificate Information: 6133 W BARROWS DR 90048

Application / Permit
22016-10000-06676
Plan Check / Job No.
B22LA04071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) 401 SF RECREATION ROOM (PERMIT 1971LA92071) TO BE CONVERTED TO ADU Per 65852.2(e)(1)(A)
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 KHUONG TRUONG
Corrections Issued 3/12/2022 KHUONG TRUONG
Plan Check Approved 4/8/2022 KHUONG TRUONG
Issued 4/18/2022 APPLICANT
Building Plans Picked Up 4/20/2022 APPLICANT
CofO in Progress 5/31/2022 ADAM ESCOTO
Permit Finaled 6/7/2022 DEROLD HAUFF
CofO Issued 6/7/2022 DEROLD HAUFF
Permit Finaled 6/7/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/15/2022 DALIA MOKAYED
Address approval Cleared 3/17/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/17/2022 JEANIE LAM
Sewer availability Cleared 3/17/2022 JEANIE LAM
HPOZ Cleared 4/4/2022 JONATHAN KAPLAN
Miscellaneous Cleared 4/4/2022 JONATHAN KAPLAN

Contact Information

Contractor New Age Construction & Remodeling; Lic. No.: 1014875-B 2729 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/25/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/25/2022 Approved ARTHUR SARGSYAN
Green Building Rough 4/25/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/25/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 4/25/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/25/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved ARTHUR SARGSYAN
Insulation 4/27/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/27/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 5/2/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/2/2022 Approved ARTHUR SARGSYAN
Shower Pan 5/2/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 5/5/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/5/2022 Approved ARTHUR SARGSYAN
Shower Pan 5/5/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 5/19/2022 Approved ADAM ESCOTO
Final 5/19/2022 Corrections Issued ADAM ESCOTO
Green Building Final 5/19/2022 Approved ADAM ESCOTO
HVAC-Final 5/19/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Final 5/19/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Not Ready ADAM ESCOTO
Smoke Detectors 5/19/2022 Approved ADAM ESCOTO
ELECTRICAL-Final 5/31/2022 Approved ADAM ESCOTO
Final 5/31/2022 OK to Issue CofO ADAM ESCOTO
HVAC-Final 5/31/2022 Approved ADAM ESCOTO
PLUMBING-Final 5/31/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved ADAM ESCOTO