6133 W BARROWS DR 90048
Certificate Information: 6133 W BARROWS DR 90048
- Application / Permit
- 22016-10000-06676
- Plan Check / Job No.
- B22LA04071
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) 401 SF RECREATION ROOM (PERMIT 1971LA92071) TO BE CONVERTED TO ADU Per 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 6/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | KHUONG TRUONG |
| Corrections Issued | 3/12/2022 | KHUONG TRUONG |
| Plan Check Approved | 4/8/2022 | KHUONG TRUONG |
| Issued | 4/18/2022 | APPLICANT |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| CofO in Progress | 5/31/2022 | ADAM ESCOTO |
| Permit Finaled | 6/7/2022 | DEROLD HAUFF |
| CofO Issued | 6/7/2022 | DEROLD HAUFF |
| Permit Finaled | 6/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 3/15/2022 | DALIA MOKAYED |
| Address approval | Cleared | 3/17/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/17/2022 | JEANIE LAM |
| HPOZ | Cleared | 4/4/2022 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 4/4/2022 | JONATHAN KAPLAN |
Contact Information
| Contractor | New Age Construction & Remodeling; Lic. No.: 1014875-B | 2729 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/2/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 5/2/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 5/2/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 5/5/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 5/19/2022 | Approved | ADAM ESCOTO |
| Final | 5/19/2022 | Corrections Issued | ADAM ESCOTO |
| Green Building Final | 5/19/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 5/19/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Final | 5/19/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | ADAM ESCOTO |
| Smoke Detectors | 5/19/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 5/31/2022 | Approved | ADAM ESCOTO |
| Final | 5/31/2022 | OK to Issue CofO | ADAM ESCOTO |
| HVAC-Final | 5/31/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 5/31/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Approved | ADAM ESCOTO |