3417 1/2 S 12TH AVE 90018
Certificate Information: 3417 1/2 S 12TH AVE 90018
- Application / Permit
- 22016-10000-06538
- Plan Check / Job No.
- B22LA04000
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- CONVERSION AND PARTIAL DEMO OF EXISTING DETACHED GARAGE, ORIGINALLY SPANNING BOTH LOTS (88 AND 90) INTO TWO SEPARATE ADU BUILDINGS EACH WITH 2 UNITS ON EACH LOT AND WITH UNFINISHED STORAGE ATTIC. (Two ADUs per State Law, CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)).
- Permit Issued
- Issued on 7/10/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | ZAW HAN |
| Corrections Issued | 3/14/2022 | ZAW HAN |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Applicant returned to address corrections | 3/21/2023 | STANLEY RAAP |
| Applicant returned to address corrections | 5/17/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 5/26/2023 | SAMUEL GONZALEZ |
| Issued | 7/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/12/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 7/8/2022 | CHRIS VONG |
| Tenant Habitability Plan | Cleared | 9/1/2022 | MICHAEL SOTO |
| Construction near power lines | Cleared | 3/7/2023 | RIDWAN HARDY |
Contact Information
| Architect | Smith,, Carl Francis; Lic. No.: C29671 | 672 S AVENUE 21 # 2 LOS ANGELES, CA 90031 |
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2024 | Corrections Issued | JUSTIN HAWLEY |
| Pre-Inspection | 7/22/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 10/7/2024 | No Access for Inspection | JUSTIN HAWLEY |
| Underground Mechanical | 10/9/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 8/28/2025 | Approved | JUSTIN HAWLEY |
| Sewer | 8/28/2025 | Approved | JUSTIN HAWLEY |
| Gas Test | 9/16/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/16/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 9/16/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 9/16/2025 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 11/7/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 11/20/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 12/5/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 2/6/2026 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 4/2/2026 | Approved | WILLIAM SIERRA |