3421 1/2 S 12TH AVE 90018

Certificate Information: 3421 1/2 S 12TH AVE 90018

Application / Permit
22016-10000-06534
Plan Check / Job No.
B22LA04000
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND PARTIAL DEMO OF EXISTING DETACHED GARAGE, ORIGINALLY SPANNING BOTH LOTS (88 AND 90) INTO TWO SEPARATE ADU BUILDINGS EACH WITH 2 UNITS ON EACH LOT AND WITH UNFINISHED STORAGE ATTIC. (Two ADUs per State Law, CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)).
Permit Issued
Issued on 7/10/2024
Issuing Office
West Los Angeles
Current Status
Issued on 7/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 ZAW HAN
Corrections Issued 3/14/2022 ZAW HAN
Building Plans Picked Up 3/16/2022 APPLICANT
Applicant returned to address corrections 3/21/2023 STANLEY RAAP
Applicant returned to address corrections 5/17/2023 CRISTINA SALAZAR
Plan Check Approved 5/19/2023 SAMUEL GONZALEZ
Issued 7/10/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/19/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/19/2022 JEANETTE VONG
Sewer availability Cleared 3/19/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/8/2022 JEANETTE VONG
Low Impact Development Cleared 7/8/2022 CHRIS VONG
Tenant Habitability Plan Cleared 9/1/2022 MICHAEL SOTO
Construction near power lines Cleared 3/7/2023 RIDWAN HARDY

Contact Information

Architect Smith,, Carl Francis; Lic. No.: C29671 672 S AVENUE 21 # 2      LOS ANGELES, CA 90031
Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2024 Corrections Issued JUSTIN HAWLEY
Pre-Inspection 7/22/2024 Approved JUSTIN HAWLEY
Pre-Inspection 10/9/2024 Approved JUSTIN HAWLEY
Special/Order Compliance 10/9/2024 Corrections Issued JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 10/17/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved ENRIQUE MIRELES
Pre-Inspection 8/11/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/14/2025 Partial Approval DEVON JACKSON
Insulation 2/6/2026 Approved JUSTIN HAWLEY
Drywall Nailing 4/13/2026 Approved JUSTIN HAWLEY
Green Building Rough 4/13/2026 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/13/2026 Approved JUSTIN HAWLEY