753 S CITRUS AVE 90036
Certificate Information: 753 S CITRUS AVE 90036
- Application / Permit
- 22016-10000-06505
- Plan Check / Job No.
- B22LA03981
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) KITCHEN, DEMOLISH AND REMOVE (2) INTERIOR WALLS LOCATED AT THE KITCHEN AND SUN ROOM TO (E) SFD COMPLY WITH DEPARTMENT ORDER effective date 06/07/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/14/2022
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2022 | FERNANDO FLORES |
| Plan Check Approved | 3/17/2022 | FERNANDO FLORES |
| Issued | 3/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| Permit Finaled | 12/13/2022 | JOHN TCHANG |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pivotal Development And Design Inc; Lic. No.: 916261-B | 5245 MINTURN AVE LAKEWOOD, CA 90712 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/4/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Deputy Drilled-In Anchors | 4/14/2022 | Partial Approval | ZEYDI STEWART |
| Footing/Foundation/Slab | 4/19/2022 | Partial Approval | ZEYDI STEWART |
| Deputy Drilled-In Anchors | 5/3/2022 | Partial Approval | ZEYDI STEWART |
| Deputy Wood Construction | 5/12/2022 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 5/17/2022 | Corrections Issued | PIERRE VEGA |
| ELECTRICAL-Rough | 5/18/2022 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 5/18/2022 | Partial Approval | PIERRE VEGA |
| Drywall Nailing | 5/23/2022 | Approved | PIERRE VEGA |
| Insulation | 5/23/2022 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 5/23/2022 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 6/23/2022 | Partial Approval | ZEYDI STEWART |
| Final | 11/17/2022 | Corrections Issued | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Ready | JOHN TCHANG |
| Smoke Detectors | 11/17/2022 | Not Ready for Inspection | JOHN TCHANG |
| Final | 12/13/2022 | Permit Finaled | JOHN TCHANG |
| Gas Test | 12/13/2022 | Approved | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 12/13/2022 | Approved | JOHN TCHANG |