1412-1414 W 216TH ST 90501

Certificate Information: 1412-1414 W 216TH ST 90501

Application / Permit
22016-10000-06465
Plan Check / Job No.
B22LA03972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 374 SF OF EXISTING SFD TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) WITH ADDITION OF 12'-4" X 15'-7", 179 sq ft ; ADD 4'-6" X 10'-6" LAUNDRY ROOM. "COMPLY WITH DEPARTMENT ORDER effective date 01/25/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/9/2022 SELLA BENYAMIN
Corrections Issued 3/9/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/4/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/27/2022 SELLA BENYAMIN
Applicant returned to address corrections 5/4/2022 MINA HABILI
Plan Check Approved 9/12/2022 MINA HABILI
Issued 9/12/2022 APPLICANT
CofO in Progress 1/31/2023 BRIAN CHRISTIAN
Permit Finaled 3/8/2023 BRUCE TODD
CofO Issued 3/8/2023 BRUCE TODD
Permit Finaled 3/8/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 7/5/2022 ANA VILLA
Roof/Waste drainage to street Cleared 7/5/2022 ANA VILLA
Eng Process Fee Ord 176,300 Cleared 7/18/2022 ANA VILLA
Sewer availability Cleared 7/20/2022 ANA VILLA

Contact Information

Contractor Owner-Builder       ,
Engineer Morales,, Wilfrido; Lic. No.: C67533 6834 GEORGIA AVE      BELL, CA 90201

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2022 Approved BRIAN CHRISTIAN
Footing/Foundation/Slab 10/20/2022 Approved BRIAN CHRISTIAN
Sewer 10/20/2022 Approved BRIAN CHRISTIAN
Underground Mechanical 11/7/2022 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 11/15/2022 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 11/15/2022 Approved BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved BRIAN CHRISTIAN
Green Building Rough 11/15/2022 Approved BRIAN CHRISTIAN
HVAC-Rough 11/15/2022 Approved BRIAN CHRISTIAN
Insulation 11/15/2022 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 11/15/2022 Approved BRIAN CHRISTIAN
PLUMBING-Rough 11/15/2022 Approved BRIAN CHRISTIAN
Drywall Nailing 11/22/2022 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 11/22/2022 Approved BRIAN CHRISTIAN
Shower Pan 11/22/2022 Approved BRIAN CHRISTIAN
Final 12/22/2022 Not Ready for Inspection ANDREW BEELI
Green Building Final 12/22/2022 Partial Approval ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 12/22/2022 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Final 1/11/2023 Corrections Issued BRIAN CHRISTIAN
Final 1/11/2023 Not Ready for Inspection BRIAN CHRISTIAN
HVAC-Final 1/11/2023 Approved BRIAN CHRISTIAN
Smoke Detectors 1/11/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 1/31/2023 Approved BRIAN CHRISTIAN
Final 1/31/2023 OK to Issue CofO BRIAN CHRISTIAN
Green Building Final 1/31/2023 Approved BRIAN CHRISTIAN
PLUMBING-Final 1/31/2023 Approved BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved BRIAN CHRISTIAN