4751-4751 1/2 E KLAMATH PL 90032

Certificate Information: 4751-4751 1/2 E KLAMATH PL 90032

Application / Permit
22016-10000-06371
Plan Check / Job No.
B22LA03916
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) Garage and Breezeway TO ADU per GCS 65852.2(e)(1)(A) All work done per WFPP
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2022 APPLICANT
Assigned to Plan Check Engineer 3/9/2022 KHUONG TRUONG
Corrections Issued 3/10/2022 KHUONG TRUONG
Plan Check Approved 4/7/2022 KHUONG TRUONG
Issued 4/25/2022 APPLICANT
Building Plans Picked Up 4/28/2022 APPLICANT
CofO in Progress 6/28/2022 ALIZAH MAYAGOITIA
Permit Finaled 8/2/2022 DEROLD HAUFF
CofO Issued 8/2/2022 DEROLD HAUFF
Permit Finaled 8/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/25/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 3/25/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 3/29/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 5/2/2022 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 5/2/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 5/6/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 5/6/2022 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 5/6/2022 Corrections Issued AMY COLIN
Gas Test 5/10/2022 Partial Approval AMY COLIN
HVAC-Rough 5/10/2022 Approved AMY COLIN
Insulation 5/10/2022 Approved AMY COLIN
Drywall Nailing 5/18/2022 No Access for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 5/20/2022 Approved RUBEN SALAS
BUILDING-Rough-Frame 6/20/2022 Approved AMY COLIN
ELECTRICAL-Final 6/20/2022 Approved AMY COLIN
Final 6/20/2022 Corrections Issued AMY COLIN
Gas Test 6/20/2022 Approved AMY COLIN
Green Building Final 6/20/2022 Corrections Issued AMY COLIN
Green Building Rough 6/20/2022 Approved AMY COLIN
HVAC-Final 6/20/2022 Approved AMY COLIN
PLUMBING-Final 6/20/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 6/20/2022 SGSOV Approved AMY COLIN
Service/Power Release 6/20/2022 Approved AMY COLIN
Smoke Detectors 6/20/2022 Approved AMY COLIN
Final 6/23/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 6/23/2022 Approved ALIZAH MAYAGOITIA
Final 6/28/2022 OK to Issue CofO ALIZAH MAYAGOITIA