906 N BEAUDRY AVE 90012
Certificate Information: 906 N BEAUDRY AVE 90012
- Application / Permit
- 22016-10000-06323
- Plan Check / Job No.
- B22LA03881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 Special Steel Cantilever Columns
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofC Issued on 9/15/2022
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2022 | JESSE VIDUYA |
| Corrections Issued | 3/14/2022 | JESSE VIDUYA |
| Quality Review Completed | 3/15/2022 | SAI KHUM |
| Applicant returned to address corrections | 4/11/2022 | JESSE VIDUYA |
| Plan Check Approved | 4/26/2022 | JESSE VIDUYA |
| Issued | 5/17/2022 | APPLICANT |
| OK for CofC | 9/14/2022 | BRUCE CAMPBELL |
| CofC Issued | 9/15/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/11/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2022 | Approved | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/2/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 6/2/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/2/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 6/14/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 6/16/2022 | Approved | BRUCE CAMPBELL |
| Final | 9/6/2022 | Corrections Issued | BRUCE CAMPBELL |
| METHANE-Final | 9/6/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 9/6/2022 | Approved | BRUCE CAMPBELL |
| Final | 9/14/2022 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | BRUCE CAMPBELL |