3516 1/2 S 11TH AVE 90018
Certificate Information: 3516 1/2 S 11TH AVE 90018
- Application / Permit
- 22016-10000-06314
- Plan Check / Job No.
- B22LA03876
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED 2-CAR (18' X 20') GARAGE (360 SF) TO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 5/22/2022
- Issuing Office
- Current Status
- CofO Issued on 12/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2022 | VIVIAN LAO |
| Corrections Issued | 3/7/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 4/29/2022 | VIVIAN LAO |
| Plan Check Approved | 5/16/2022 | VIVIAN LAO |
| Issued | 5/22/2022 | APPLICANT |
| CofO in Progress | 12/13/2023 | JUSTIN HAWLEY |
| Permit Finaled | 12/15/2023 | DEROLD HAUFF |
| CofO Issued | 12/15/2023 | DEROLD HAUFF |
| Permit Finaled | 12/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | CINDY QI |
| Sewer availability | Cleared | 3/17/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | CINDY QI |
| Construction within easement | Cleared | 5/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakhamaneshi,, Manouchehr; Lic. No.: C88083 | 12935 ALCOSTA BLVD PO BOX 1435 SAN RAMON, CA 94583 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/26/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 8/5/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/10/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/7/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 10/7/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 10/7/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/7/2022 | Conditional Approval | FREDDIE RIVERA |
| Underground Mechanical | 10/7/2022 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/7/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/7/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 11/7/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 11/7/2022 | Approved | STUART CHAPMAN |
| Sewer | 11/7/2022 | Approved | STUART CHAPMAN |
| Insulation | 11/17/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/17/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 11/17/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/5/2022 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 9/22/2023 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 10/16/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 10/16/2023 | Approved | CALEB MEISTER |
| Service/Power Release | 12/5/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 12/13/2023 | Approved | JUSTIN HAWLEY |
| Final | 12/13/2023 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 12/13/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 12/13/2023 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 12/13/2023 | Approved | JUSTIN HAWLEY |